1224.54   CONSTRUCTION PROCEDURE AND MATERIALS.
   The subdivider shall design and construct improvements not less than the standards outlined in these regulations and in accordance with the 12-month construction period limitation. The minimum requirements for materials shall be in accordance with the standards of the current volume of Construction and Material Specifications of the State of Ohio Department of Transportation, and the requirements of the Environmental Protection Agency, when applicable. All work shall be done under City supervision and inspection, and costs for inspection in connection with the required improvements and unanticipated soil conditions, drainage problems, etc., shall be borne by the subdivider. A bond or check for the estimated amount of these inspection costs, as approved by the City Manager, shall be posted or paid prior to final recording of the final plat by the County Recorder.
(Ord. 12-02. Passed 7-8-02.)