§ 153.078 INSPECTIONS.
   The Village Engineer shall inspect the site and shall either approve that portion of the work completed or shall notify the permittee that the same fails to comply with the approved plan.
   (A)   When it is found by inspection that conditions are not substantially as stated or as shown in the plan, the Village Engineer may order that further work be stopped until non-conforming conditions are corrected.
   (B)   Plans for grading work and the site development permit shall be maintained at the site during progress of the grading.
   (C)   Until the final inspection is made, a permit issued by the village indicating permission to construct has been granted by the village shall be prominently displayed on the front property line of the site involved and be visible from the street on which the site fronts.
   (D)   In order to obtain inspections in accordance with the following schedule, the permittee shall notify the Village Engineer at least 2 full working days before the inspection is to be made for:
      (1)   Stripping and clearing;
      (2)   Rough grading, i.e., when all rough grading has been completed;
      (3)   Final grading; and
      (4)   Final inspection, i.e., when all work, including installation of all drainage and other structures and required planting, has been completed.
(Ord. 2007-15, passed 7-10-2007; Am. Ord. 2021-03, passed 3-9-2021) Penalty, see § 153.999