1165.12 STORM WATER MANAGEMENT PLANS.
   (a)   Purpose. This section outlines the process to be used to review applications for storm water management plans required pursuant to Chapter 1174 Storm Water Management Regulations.
   (b)   Initiation. Pursuant to Subsection 1165.02(a) Authority to File Applications, any person having authority to file applications may initiate an application for storm water management plan review.
   (c)   Process.
      (1)   Step 1 - Application. The applicant shall submit an application in accordance with Section 1165.02 Common Review Requirements and with the provisions of this chapter.
      (2)   Step 2 - Review of Application by City Engineer. Upon receipt of an application for storm water management plan review, the City Engineer shall review the application for completeness.
      (3)   Step 3 - Decision by City Engineer. The City Engineer shall review the plans and take one of the following actions:
         A.   Approve the Storm Water Management Plan within 20 working days of receipt of a complete application;
         B.   Return the Storm Water Management Plan with comments and recommendations for revisions within 20 working days of receipt of a complete application; or
         C.   Deny the Storm Water Management Plan because of deficiencies and issue a report stating specific problems within 20 working days of receipt of a complete application.
   (d)   Plan Revisions. At the time of receipt of a revised plan, another review period of 20 working days shall begin.
   (e)   Expiration. Approved plans shall remain valid for two years from the date of approval. After two years the plan(s) approval automatically expires if no work has been initiated.
(Ord. 7675. Passed 11-11-14.)