§ 93.05 BACKFILLING.
   (A)   Unimproved streets or alleys shall be refilled with dirt, after which tamping shall come to within one foot of the top of the surface dug into and the remaining one foot shall be filled with material approved by the City Street Department.
   (B)   Improved streets or alleys shall be filled in the following manner:
      (1)   Six inches of approved fill shall be first placed in the hole so cut and dug;
      (2)   The fill material shall be compacted to a point below grade as approved by the Street Department; and
      (3)   The hole shall then be capped with pavement material as directed by the Street Department.
   (C)   The above operations set out in division (A) above shall be done in a workmanlike manner, and to the approval of the Street Commissioner, and shall be completed as soon as possible, but not to exceed 30 days, weather permitting.
(Prior Code, § 93.05)