(A)
SAMPLING, MONITORING AND REPORTING
| |||
Noncompliance | Circumstances | Range of Response |
SAMPLING, MONITORING AND REPORTING
| |||
Noncompliance | Circumstances | Range of Response | |
1. | Failure to sample, monitor or report | Isolated or infrequent | Notify with phone call. May require report within 10 days |
2. | Failure to sample, monitor, report or notify | IU does not follow through with verbal action | (LOV) Letter of violation. No response can lead to significant noncompliance, then formal action |
3. | Failure to notify of effluent violation or slug discharge | Isolated or infrequent, no known effects | Notify with phone call. Must notify within 10 days if no formal action will be taken |
4. | Failure to notify of effluent violation or slug discharge | Frequent or continued violations | LOV, Formal action (Compliance schedule etc.) |
5. | Failure to notify to effluent violation or slug discharge | Known environmental or POTW damage results | LOV, Formal action, but can include emergency conditions which accelerate enforcement actions leading to termination of service |
6. | Minor sampling, monitoring or reporting errors (typographical) | Isolated or infrequent | Phone call, corrections made on next submittal |
7. | Major sampling, monitoring or reporting deficiencies | Isolated or infrequent | LOV, corrections must be made on next submittal |
8. | Major reporting deficiencies | Continues or remains uncorrected 3 0 or whenever an LOV is issued that requires a response and the Industrial User fails to respond, the next level of enforcement will be taken. | LOV, followed by formal action more clays |
COMPLIANCE SCHEDULES | |||
9. | Reporting false information | Any instance SNC | LOV, formal action and if necessary cease and desist with fines and penalties assessed |
10. | Missed milestone date | Will not cause late final date or other milestone dates | LOV. Response required within 10 days |
11. | Missed milestone date | Will result in other missed milestone dates Violation for good or valid cause | LOV. Response required within 10 days |
12. | Missed milestone date | Will result in other missed milestone dates no go-5 | Phone call, LOV, the cease & desist with civil |
14. | Missed final date | 90 clays or more outstanding. Failure or refusal to comply without good or valid cause | Civil penalties, injunction and possible termination of service |
15. | Failure to install monitoring equipment | Continued - SNC | Phone call, LOV formal action, (informal meeting 10 clays Whenever an LOV is issued that requires a response and the Industrial User fails to respond, the next level of enforcement will be taken. |
ENFORCEMENT RESPONSE GUIDE | |||
Effluent Limits | |||
16. | Exceed final limit | Infrequent or isolated isolated | Phone call, may require letter within 10 days |
17. | Exceed final limit | Infrequent or isolated Major | Phone call, may require letter within 10 days |
18. | Exceed final limit | 4 or more violations of the same effluent limits or 2 violations which exceed TRC | Phone call, LOV formal action (compliance schedule & if necessary cease & desist with civil penalties recommended |
19. | Exceed final limit | Results in known environmental or POTW damage | Phone call, LOV, formal action (Compliance schedule & if necessary cease & desist with civil penalties recommended |
20. | Report slug load | Isolated without known damage | LOV. May require letter within 10 days |
21. | Report slug load | Isolated with known interference, pass through or damage | Phone call, LOV, formal action, (informal meetings with possible penalties) |
22. | Report slug load | Recurring | LOV, Formal action, (informal meeting, compliance schedule, possible penalties) |
23. | Discharge without permit or approval | One time without known environmental POTW damage | Phone call, LOV, cease & desist if necessary |
24. | Discharge without permit or approval | One time which results in environmental damage or continuing violation | LOV, Formal action (penalty, but could include emergency conditions that accelerate enforcement action leading to termination |
25. | Discharge without permit | Continuing violation with known environmental or POTW damage | Formal action (Civil penalties, cease & desist, termination of service. Request criminal investigation) whenever an LOV is issued that requires a response and the Industrial User fails to respond, the next level of enforcement will be taken. |
ENFORCEMENT RESPONSE GUIDE | |||
Noncompliance Detected through Inspections or Field Investigation | |||
26. | Major violation of analytical procedure | No evidence of intent | Phone call or LOV |
27. | Major violation of analytical procedure | Evidence of intent or negligence | Phone call, LOV, formal action (informal meeting with possible penalties) |
28. | Minor violation of permit conditions | No evidence of negligence or intent | Phone call |
29. | Minor violation of, permit conditions | Evidence of intent or negligence | LOV, SNC, formal action may be taken |
30. | Major violation of permit conditions | Evidence of negligence | LOV, SNC, with possible formal action (civil penalties, cease & desist, possible criminal investigation and/or termination of service) |
Where an LOV is issued that requires a response and the industrial user fails to respond, the next level of enforcement will be taken. | |||
(B) This Range of Enforcement Guide addresses a broad range of pretreatment violations. It is not intended to cover all types of violations. The responses in this Guide are suggested responses. They are equally effective. The measure of the effectiveness of an enforcement response includes:
(1) Whether the non-complying source returns to compliance as expeditiously as possible.
(2) Whether the enforcement response establishes the appropriate deterrent effect for the particular violator and for other potential violators.
(3) Whether the enforcement response promotes fairness to government treatment as between comparable violators, as well as between complying and noncomplying parties.
(C) This Guide has been developed for guidance and is not intended to create legal rights or obligations, or to limit the enforcement discretion of the City of Crawfordsville, Indiana.
(Ord. 4-1999, passed 3-8-99; Am. Ord. 12-2012, passed 8-13-12; Am. Ord. 16-2016, passed 7-11-16)