§ 156.03 PAVEMENT REPAIR SECTION AROUND MANHOLES AND WATER VALVES.
   (A)   Asphalt pavement section repair around the sewer manholes and water line valve boxes should be as shown on the attached detail incorporated in § 156.04.
   (B)   Prior to performing the asphalt repair, a clean cut should be performed around the manhole or valve box. The asphalt cut should be performed in a diamond shape according to the traffic direction as shown on the standard detail incorporated in § 156.04.
   (C)   After removing the asphalt pavement thickness, the exposed soils should be scarified to a depth of eight inches. The scarified soil should be compacted to 95% of ASTM D698 (Standard Proctor) maximum dry density at a moisture content within 3% above or below the ASTM D698 optimum moisture content.
   (D)   Steel reinforcing rebar shall be grade 40 steel, and concrete shall have a minimum compressive strength of 4,000 pounds per square foot.
   (E)   Traffic should not be allowed to travel on the concrete pavement section until the concrete has obtained a minimum compressive strength of 3,000 pounds per square foot.
(Ord. 233, passed 12-10-1992) Penalty, see § 10.99