1199.01 GENERAL.
   (a)    Preconstruction Conference. The subdivider shall, at least one week prior to construction of any improvements, schedule a preconstruction conference with the Service Director. Items to be covered at the preconstruction conference should include proposed construction schedule, materials, methods, etc.
   (b)    Construction Schedule. The subdivider should notify the Service Director at least one (1) week prior to any construction work and also indicate the scheduled duration of such work. This schedule should be updated, as required, on a weekly basis.
   (c)    Construction Inspection. The Service Director shall be responsible for the supervision of the inspection of improvements constructed under these subdivision regulations. The subdivider shall be responsible for maintaining sufficient stakes, control points, etc., as may be necessary for such inspection and shall also be responsible for maintaining, at all times, one (1) approved set of construction drawings and specifications at the construction site. The subdivider shall also be responsible for maintaining (and updating) the record or as-built drawings at the construction site.
   (d)    Material Testing and Documentation. The subdivider shall provide all material testing and documentation deemed necessary by the Service Director to ensure that the improvements meet the required construction and material standards. The costs of all such materials testing and documentation shall be the responsibility of the subdivider.
   (e)   Grading Work. All grading work shall be performed in such a manner as to preserve and reuse existing topsoil and to preserve and save, wherever possible, existing trees, wooded areas and other natural features. All areas shall be graded to provide positive drainage to an adequate and suitable drainage outlet such as a storm sewer or natural water course. If proposed grading would increase the amount of stormwater runoff to an adjacent lot, a suitable stormwater collection system or other method approved by the Service Director shall be provided to eliminate such increase in stormwater runoff to the adjacent lot.
(Ord. 0-37-95. Passed 5-15-95.)