§ 152.009 DEADLINE FOR ACTION.
   It is the intent of the city to comply with state requirements for timely review and actions requiring formal approval by the city. Information submissions and applications must be determined by the city to be complete before a timeline for action is initiated. In the event the city cannot act upon a request within a 60-day timeframe, the city will notify an applicant in writing that action will be completed within 120 days of the date the application was accepted by the city. In the event that multiple approvals are involved in any action, such as zoning ordinance amendment, comprehensive plan amendment, environmental review, preliminary plat and final plat, each action shall require a separate, independent timeline for action.
(Ord. 141, passed 7-7-1997, Ord. passed 4- -2007)