(A) Each user must notify the Superintendent or Director of any planned significant changes to the user's operations or system which might alter the nature, quality, or volume of its wastewater at least 30 days before the change. The permittee shall not begin the changes until receiving written approval from the Control Authority and/or Municipality. See § 52.055 for other reporting requirements.
(B) The Superintendent or Director may require the user to submit such information as may be deemed necessary to evaluate the changed condition, including the submission of a wastewater discharge permit application under § 52.041.
(D) For purposes of this requirement, significant changes include, but are not limited to, flow or pollutant increases of 20% or greater, and the discharge of any previously unreported pollutants.
(Ord. passed 11-8-94; Am. Ord. 2008-05-02, passed 5-5-08; Am. Ord. 2013-04-01, passed 4- 1-13; Am. Ord. 2018-07-07, passed 7-16-18)