The Uniform and Consolidated Fee Schedule to be assessed and collected by the Building Commissioner's office is set forth below.
Commercial | |
Commercial - General Permit Fees | |
Structures - New Construction | Fee/sq. ft. |
Plan review (minimum $50) | $0.03 |
Occupancy Group A, H and I + inspections | $0.90 |
Occupancy Group B and R + inspections | $0.80 |
Occupancy Group M + inspections | $0.70 |
Occupancy Group F + inspections | $0.60 |
Occupancy Group S + inspections | $0.50 |
Air supported structures + inspections | $0.03 |
Tenant Finish or General Build-out | |
Plan review (minimum $50) | $0.05 |
Tenant finishes - Group A, H and I | |
Occupancy (<than 5,000 SF) | $0.50 |
Occupancy (5,001 - 10,000 SF) | $0.35 |
Occupancy (>than 10,001 SF) | $0.20 |
Tenant Finishes - Group B, R, M & S | |
Occupancy (<than 5,000 SF) | $0.40 |
Occupancy (5,001 - 10,000 SF) | $0.30 |
Occupancy (>than 10,001 SF) | $0.20 |
Certificate of occupancy | $200 |
Demolition (requires asbestos survey) | $100 |
Inspections | $60 |
Re-inspections | $120 |
*Residential | |
Residential - General Permit Fees | |
Structures - New Construction | Fee |
Plan review | $35 |
One and two family dwelling | $0.020/sq. ft. |
Residential remodel | |
No increase in square footage | $50 |
Plus per square foot of new space | $0.15 |
Certificate of occupancy | $100 |
Demolition | $50 |
Inspections | $25 |
Re-inspections | $50 |
*Square footage is the sum of all floor levels, garages and attachments | |
Electrical | |
Commercial - Electrical Permit Fees | Per Unit |
New/Alterations - $60 +amps + inspection | |
Amps | $0.70 |
Temporary service - 100 amps | $60 |
Temporary service - 200 amps | $120 |
Meter base inspection | $60 |
Inspection | $60 |
Re-inspection | $120 |
Residential - Electrical Permit Fees | Per Unit |
New/Alterations - $60 +amps + inspection | |
Amps | $0.40 |
Temporary service - 100 amps | $50 |
Temporary service - 200 amps | $100 |
Meter base inspection | $40 |
Inspection | $30 |
Re-inspection | $60 |
Plumbing | |
Commercial - Plumbing Permit Fees | |
New Construction/Alterations/Remodel s | Per Unit |
Per fixture unit as defined by IBC 1st fixture | $60 |
Each additional unit | $10 |
Water heater | $50 |
Backflow preventer | $50 |
Inspection | $60 |
Re-inspection | $120 |
Residential - Plumbing Permit Fees | |
New Construction/Alterations/Remodel s | Per Unit |
Per fixture unit as defined by IBC 1st fixture | $40 |
Each additional unit | $5 |
Water heater | $30 |
Backflow preventer | $30 |
Inspection | $30 |
Re-inspection | $60 |
Mechanical - HVAC | |
Commercial - Mechanical and HVAC Fees | |
Furnace (new) | $70 |
Furnace (replacement) | $35 |
Air conditioner (new) | $70 |
Air conditioner (replacement) | $35 |
Combination or split systems | $90 |
PTAC units | $70 |
Roof top unit (RTU) | $100 |
Air handlers | $70 |
Hood suppression systems | $100 |
Inspection | $60 |
Re-inspection | $120 |
Residential - Mechanical and HVAC Fees | |
Furnace (new) | $60 |
Furnace (replacement) | $30 |
Air conditioner (new) | $60 |
Air conditioner (replacement) | $30 |
Combination or split systems | $60 |
PTAC units | $50 |
Inspection | $30 |
Re-inspection | $60 |
Fire Safety | |
Commercial Fire System | |
New construction/New installations | Fees |
Fire suppression systems (covered area) plus $0.50/head new or relocation | $0.02/ft 2 |
Riser fee (new) | $250 |
Riser inspection fee (existing) | $100 |
Fire alarm | $180 |
Inspection | $100 |
Re-inspection(s) | $200 |
Commercial Roofing Systems | |
Roofing - Pertains to roof components only | Fees |
Shingled | $0.05/ft 2 |
Metal | $0.07/ft 2 |
EPDM, TPO, TPE or built up | $0.10/ft 2 |
Inspection | $50 |
Re-inspection | $100 |
Residential Roofing Systems | |
Roofing - Pertains to roof components only | Fees |
Shingled | $50 |
Metal | $75 |
Inspection | $30 |
Re-inspection | $60 |
Manufactured Home Installation | |
Permit | Fees |
Includes inspection for electrical service, tie down, egress decks & stairs and HVAC | $200 |
Inspection | Included |
Re-inspection | $100 |
Residential Rental Property Registration and Inspection | |
Registration | Fees |
Rental unit (not part of a rental unit community) | $5/yr |
Rental unit community | $5/yr |
Inspection | Fees |
Third-party inspection | $0.00 |
Regularly scheduled inspection* | $200/u nit |
Rescheduling fee | $100/u nit |
Re-inspection | $300/u nit |
*Conducted by the Enforcement Authority | |
Planning and Zoning | |
Land Use Petitions | |
Zoning map change | |
Less than 5 acres | $500 |
5 acres or more | $750 |
Variance | |
Use* | $500 |
Development standards | |
Residential District (R1, R2)* | $100 |
Plus each additional variance | $25 |
All other districts* | $200 |
Plus each additional variance | $50 |
Special exception* | $250 |
Parking waiver* | $150 |
Administrative appeal* | $100 |
Amendment to commitment | $300 |
Development plan | |
Minor* | $300 |
Amended minor* | $150 |
Major* | $500 |
Plus each acre over 1st acre | $100 |
Amended major* | $250 |
Plus each acre over 1st acre | $25 |
*For items with asterisk add $5 for sign | |
Plat | |
Minor* | $300 |
Major* | $750 |
Plus per lot | $10 |
South Clarksville Mixed Use District | |
District development plan Master site | $500 |
District development plan Building site | $500 |
Plus each acre over 1st acre | $100 |
Waiver | |
Minor | $50 |
Design (non- material) | $150 |
Design (material) | $250 |
Wireless communication facility | $100 |
Fill permit | $100 |
*For items with asterisk add $50 for public notification | |
Signs | |
Permanent (per sign face) | $60 |
Temporary (per sign) | $20 |
Accessory Structure | |
Fence | $25 |
Shed, carport, pergola | $30 |
Garage (per car space) | $55 |
Pool | |
Aboveground | $60 |
Inground | $125 |
(Ord. 2019-G-06, passed 4-16-19; Am. Ord. 2019-G-17, passed 8-6-19; Am. Ord. 2022-G-06, passed 4-19-22; Am. Ord. 2022-G-14, passed 11-1-22; Am. Ord. 2022-G-17, passed 12-20-22; Am. Ord. 2023-G-13, passed 10-17-23)