General.
(a) Maintain on-site a full set of project drawings for purpose of recording as- constructed conditions.
(b) Information should be legibly recorded as construction progresses.
(c) Clearly and completely identify any field changes from the original drawings.
(d) Actual, as-constructed elevations shall be obtained on all structures such as manholes, wet well, etc. Invert depths shall be recorded at each structure. All elevations shall be referenced to NAVD 88.
(e) Show horizontal and vertical location of any existing underground utilities encountered during construction.
(f) Submit document to the city prior to final acceptance.
(g) All new features shall be surveyed utilizing survey grade GPS equipment and digital file with all surveyed information shall be provided to the city.
(h) A digital CADD file shall be provided to the city that contains all the features constructed with the updated as-built information along with survey data.
(i) The city shall have the right to employ an independent survey firm to verify the “As-Constructed” drawings submitted by the developer at the end of the project. If components or the drawings are determined to be incorrect, the developer shall have all items corrected to obtain final approval by the city. Developer will also be responsible for reimbursing the city for all associated costs related to verification, review, and other costs arising from any corrections having to be made in order to provide correct plans and files to the city.
(Ord. of 11-7-16, No. 10-16)