Sec. 5-3-60   “As-constructed’ drawings.
   (a)   General.
      (1)   Maintain on-site a full set of project drawings for purpose of recording as-constructed conditions.
      (2)   Information should be legibly recorded as construction progresses.
      (3)   Clearly and completely identify any field changes from the original drawings.
      (4)   The depth of all force mains shall be recorded at all roadways, waterway crossings, utilities crossings and all other areas as needed to accurately define the vertical location of the force main. A minimum of one depth shall be recorded on each 100 feet of pipe installed. Depth shall be referenced to finished surface grades.
      (5)   Show horizontal and vertical location of any existing underground utilities encountered during construction.
      (6)   Submit document to the city prior to final acceptance.
      (7)   All new features shall be surveyed utilizing survey grade GPS equipment and digital file with all surveyed information shall be provided to the city.
      (8)   A digital CADD file shall be provided to the city that contains all the features constructed with the updated as-built information along with survey data.
      (9)   The city shall have the right to employ an independent survey firm to verify the “as-constructed” drawings submitted by the developer at the end of the project. If components or the drawings are determined to be incorrect, the developer shall have all items corrected to obtain final approval by the city. Developer will also be responsible for reimbursing the city for all associated costs related to verification, review, and other costs arising from any corrections having to be made in order to provide correct plans and files to the city.
(Ord. of 11-7-16, No. 10-16)