The following construction may occur without meeting the underground installation requirements:
(A) Transmission lines and betterment to existing utilities together with related switch yards, substations and related equipment;
(B) Repair or improvement of existing utility poles and wires by the serving utility, provided that activity is not initiated on request of or by a developer;
(C) Installation of new utility poles and wires or relocation of existing utility poles and wires not initiated by a developer;
(D) Pad-mounted transformers or pull boxes, service terminals, pedestal type telephone terminals, telephone splice closures or similar on-the-ground facilities attached to existing overhead facilities which are used for the purpose of connecting an underground system with the existing facilities;
(E) Temporary service facilities, such as facilities to furnish emergency service during an outage, facilities to provide service to construction sites or other service of a limited duration, such as to a fair, carnival, outdoor exhibit or function where the facilities will be installed for a temporary period only; and
(F) New service drops or improvement of existing service drops from existing overhead lines to single family residential customers, except when underground service is required by the Town of Chino Valley subdivision regulations.
(2001 Code, § 7-12-3)