§ 142-21 INSPECTION SCHEDULE AND REPORTS.
   (A)   The owner/developer shall notify the town designee for stormwater inspection at least 48 hours before beginning any work in conjunction with site development, the stormwater management plan and completion of construction.
   (B)   Regular inspections shall be made and documented for each ESD planning technique and practice at the stages of construction specified in the design manual by the town, its authorized representative, or a certified engineer licensed in the State of Maryland. At a minimum, all ESD and other nonstructural practices shall be inspected upon completion of final grading, the establishment of permanent stabilization, and before issuance of use and occupancy approval.
   (C)   Written reports shall be prepared for every inspection and shall include:
      (1)   The date and location of the inspection;
      (2)   Whether construction was in compliance with the approved stormwater management plan;
      (3)   Any variations from the approved construction specifications; and
      (4)   Any violations that exist.
   (D)   The owner/developer and on-site personnel shall be notified in writing when violations are observed. Written notification shall describe the nature of the violation and the required corrective action.
   (E)   Work shall not proceed until the work previously completed is approved by the appropriate inspector, and the inspector furnishes the developer with the results of the inspection report. The inspector should provide copies of the inspection report to the developer as soon as possible after completion of each required inspection.
(Ord. 08-2010, passed 11-1-2010)