§ 155.050 BEGINNING CONSTRUCTION OF SUBDIVISION IMPROVEMENTS.
   Approval of the construction plans shall give the subdivider the right to begin construction of the Subdivision lmprovements, but only after scheduling a pre-construction conference with the village's consulting engineer, engineer of record, construction superintendent, and the resident observer for the project. Construction must be started within one year of approval of the construction plans. If construction is not started within the year, re-approval by the village’s consulting engineer shall be required before construction is started.
(Ord. 94-01, passed 1-25-94; Am. Ord. 16-35, passed 6-28-16)