1113.29 PRECONSTRUCTION SUBMITTAL.
   (a)   Purpose. The purpose of the preconstruction submittal is to review the plans and other documents for compliance with final terms and conditions of plan approval, permit issuance requirements, insurance coverages, performance guarantee and other administrative requirements and approval thereof before work begins.
   (b)   Conformance with Previous Submittals. A preconstruction submittal shall not be approved unless it substantially conforms with previously approved submittals. A variance by the final approving authority from an approved plan or Municipal specification may be requested as part of the submittal.
   (c)   Submittal Contents. A preconstruction submittal shall include the following as required:
   Approved construction drawings for site work.
   Approved architectural construction drawings for all buildings and structures.
   Plumbing schematic drawing.
   Plans for the installation of automatic fire suppression systems and fire alarm system.
   Contractor registration (general contractor).
   List of all subcontractors for the project.
   Performance Guarantees (as required).
   Certificate of liability insurance naming the City of Chardon as an additional insured.
   Copy of approved Site Development Permit.
   Copy of approved Zoning Certificate.
   Copy of approved Building Permit from the Geauga County Building Department.
Copy of approval from County Health Department or Ohio EPA for on-site sewage treatment facilities (if applicable).
   Copy of approved Ohio EPA Permit to Install Sewers.
   Copy of approved Ohio EPA Permit to Install Water Lines.
   Copy of approved NPDES Permit for storm water discharge from Ohio EPA.
   Copy of approved Clean Water Act § 404 Permit from U.S. Army Corps of Engineers.
Manufacturer's catalog cut-sheets for all materials to be used in the installation and construction of a water line, sewer line, traffic signal equipment, street lights, traffic control signs, pavement markings and storm water management structures or devices.
   Certifications for all pipe bedding and granular backfill material;
   Concrete and asphalt mix designs for streets, sidewalks, driveways and driveway aprons.
   Application for Water Service.
   Application for Sanitary Sewer Service.
    Application for Storm Sewer Service.
   Payment of all fees and deposits which are due and payable.
   Final construction schedule.
Other plans and documents which are necessary to thoroughly and properly evaluate the submittal and proposed work and compliance with Municipal ordinances, standards and specifications.
   (Ord. 2635. Passed 1-13-11.)