925.56 PROVIDE FOR FUTURE CONNECTIONS.
   When new sanitary sewer mains are to be constructed the following provisions for future connections shall be made.
   (a)   When the required size of the service lateral to a lot or building site can be predetermined, a stubbed service lateral, conforming to Municipal specifications, shall be installed for the future use of said lot and/or building site. The connection shall be made and the service lateral extended to the street right of way line. The terminus of the lateral shall be capped and its location marked with a wood pole or other device approved by the Authority having jurisdiction. When sewer lines are not installed within a public right of way the required lateral shall be installed to a point approved by the Authority having jurisdiction. When the service lateral size cannot be predetermined the future applicant for sanitary sewer service shall be required to conform to Section 925.57 (Street Opening and Boring).
   (b)   When the subject property abuts undeveloped lands, the developer shall extended sewer mains, and easements for same, to the property line in a manner, and in such locations, as the Approving Authority for the subject project may reasonably require in accordance with accepted engineering standards and practices so as to provide for the continuation of service to said undeveloped lands in the future. When, in accordance with the Land Planning and Development Regulations, the present construction of said sewer lines is not warranted, the developer shall be required to provide the necessary sewer line easements to connect with said abutting lands.
      (Ord. 1327. Passed 5-9-91.)