(a) Upon submission of the complete application for site plan review to the Zoning Inspector, the application shall be transmitted to the Planning Commission for review pursuant to Section 1146.03, "Site Plan Review Guidelines".
Notice of all public meetings shall be given as required by State law, and the Planning Commission may hold a public hearing on any site plan review application.
(b) The Planning Commission shall act upon all site plans within thirty-five (35) days after the receipt of the complete application from the Zoning Inspector. The Planning Commission may approve, disapprove or approve with modifications the site plan as submitted. Within the said thirty-five (35) day period, a majority of the members of the Planning Commission present at a meeting thereof may vote to extend the review period up to an additional sixty (60) days.