2-2.04 Replacing Existing Temporary Street and Alley Surfaces:
   (A)   General. For the purpose of this specification, all existing street and alley surfaces shall be considered temporary except:
      (1)   Concrete or brick pavements; and
      (2)   An asphaltic concrete or a bituminous treated surface over a soil cement, concrete, crushed stone or selected gravel base. Specifically included as temporary street surfaces shall be compacted earth, cinders, shale, mixtures of gravel and earth or crushed stone and earth, whether or not these respective materials are further stabilized by road oil or bituminous surface treatment.
   (B)   Where, in the opinion of the Engineer, the conduit is located in the traveled portion of the temporary street or alley traveled surface, a new temporary surface shall be constructed over the trench, as specified in § 2-2.01. After this surface has been placed, it shall be maintained by the Contractor until final restoration is authorized. Just prior to final restoration, the entire width of the street to be restored shall be scarified. For final surface restoration, the Contractor shall apply a bituminous treatment to the entire width of the traveled surface, as ordered by the Engineer. The bituminous treatment shall consist of the application of a bituminous prime coat and a bituminous surface treatment corresponding to the materials and construction methods described in the Indiana State Highway Specifications for bituminous surface treatment.
   (C)   The Engineer reserves the right to order the omission of bituminous surface treatment in any locations where such omission may be, in his opinion, in the public interest.