6-2-3   PRIVATE SEWAGE DISPOSAL.
   1.   Where a public sanitary or combined sewer is not available under the provision of Section 6-2-2(4), the building sewer shall be connected to a private sewage disposal system complying with the provisions of this section.
   2.   Before commencement of construction of a private sewage disposal system the owner shall first obtain a written permit signed by the Superintendent. The application for such permit shall be made on a form furnished by the City, which the applicant shall supplement by any plans, specifications, and other information as are deemed necessary by the Superintendent.
   3.   A permit for a private sewage disposal system shall not become effective until the installation is completed to the satisfaction of the Superintendent. The Superintendent shall be allowed to inspect the work at any stage of construction and, in any event, the applicant for the permit shall notify the Superintendent when the work is ready for final inspection, and before any underground portions are covered. The inspection shall be made within 72 hours of the receipt of notice by the Superintendent.
   4.   The type, capacities, location, and layout of a private sewage disposal system shall comply with all recommendations of the Department of Natural Resources of the State of Iowa and the County Health Department. No permit shall be issued for any private sewage disposal system employing subsurface soil absorption facilities where the area of the lot is less than 1,500 square feet. No septic tank or cesspool shall be permitted to discharge to any natural outlet.
   5.   At such times as a public sewer becomes available to a property served by a private sewage disposal system, as provided in 6-2-2(4), a direct connection shall be made to the public sewer in compliance with this Ordinance, and any septic tanks, cesspools, and similar private sewage disposal facilities shall be abandoned and filled with suitable material.
(Code of Iowa, Sec. 364.12(3)(f))
   6.   The owner shall operate and maintain the private sewage disposal facilities in a sanitary manner at all times, at no expense to the City.
   7.   No statement contained in this section shall be construed to interfere with any additional requirements that may be imposed by the County Health Officer.
   8.   When a public sewer becomes available, the building sewer shall be connected at the building owner's expense, to said sewer within sixty (60) days and the private sewage disposal system shall be cleaned of sludge and filled with clean bank-run gravel or dirt.