A. Prior to the commencement of any work requiring a certificate of no effect, the owner shall file an application for such a certificate with the department.
B. No permit shall be issued for such proposed work until a certificate of no effect has first been issued by the department. The certificate of no effect required by this act shall be in addition to, and not in lieu of, any permit that may be required by any other city ordinance, rule or regulation.
C. The director shall approve, approve with modifications, request additional information, or refer the certificate of no effect within ten business days after submission of a complete application.
1. A copy of any decision shall be communicated in writing to the applicant.
2. If the decision is to request additional information, modify the application, or deny the application, a written explanation, setting for the basis of the decision, shall be communicated in writing to the applicant.
3. If a certificate of no effect is referred, within 30 days the application will be forwarded to the historic preservation commission for consideration as a certificate of appropriateness.
(Ord. 1397.17.47 § 3 (part), 2017; Ord. 1397.17.32 § 2 (part), 2004)