Within 90 days of the adoption of an initial franchise agreement, Franchisee shall meet with the town Manager and/or his/her designee to review the status of the initial system's construction plan and 18 month construction schedule. Within 30 days following this meeting, the grantee shall apply for any needed contracts for use of poles. Within 30 days after completion of the make-ready survey identifying the routes of the system facility, the grantee shall apply for all additional licenses from the state, town, or other necessary parties, such as the railroads for crossing under or over their property. In any event, all necessary applications for permits, licenses, certificates and authorizations shall be applied for in a timely fashion so that such filing and processing shall not interfere with or cause delay with the construction scheduled as outlined in the franchise. Failure to make such timely application and timely filing shall constitute a substantial violation of this chapter.
(Ord. No. 04-009, § 6-33, 8-26-2004)