(A) When cut sheets are required by the Engineer, sewer construction stakes shall be located at angle points, grade breaks, cleanouts, wyes, structures and at a 50-foot maximum spacing. An additional stake will also be required at property line and at connection point with building plumbing (building drain).
(B) The stakes shall be offset from the center line of the sewer at a safe distance from the edge of the trench but in no case greater than ten feet unless authorized by the Engineer. The stakes will be marked with offset and station only.
(C) When the sewer is to be constructed to property line only, the Engineer may require a stake to be set at the point prior to construction.
(Ord. 2019-02, passed 4-25-2019)