§ 33.332 GRADE STAKES.
   (A)   Unless otherwise required by the Engineer, sewer construction stakes will be located at 50 feet maximum intervals, except that on horizontal curves and on sewers with a slope flatter than 0.0034 feet per foot the maximum spacing will be 25 feet.
   (B)   (1)   The stakes shall be offset from the center line of the sewer at a safe distance from the edge of the trench, but in no case greater than ten feet unless authorized by the Engineer.
      (2)   The stakes will be marked with offset distance and station only.
(Ord. 2019-02, passed 4-25-2019)