§ 33.265 SITE CLEANUP.
   (A)   Surplus pipeline material, tools, remaining material from site preparation and the like shall be removed by the contractor, and all dirt, broken pavement, rubbish and excess earth from excavation shall be hauled to an approved disposal site provided by the contractor, and the construction site left clean, to the satisfaction of the Engineer.
   (B)   Replaceable items, such as fences, signs, landscaping and the like, requiring removal during construction operations must be replaced in kind by the contractor at his or her expense or disposed of as noted on the approved plans. Driveway areas or other improvements requiring removal and/or excavation will be restored in accordance with the requirements of the agency having local jurisdiction to a condition equivalent to their original condition, and to the satisfaction of the Engineer.