§ 33.224 ORDER OF WORK.
   The following order of work shall be performed by the contractor following construction of the sewer mains and laterals, manholes and sewer system appurtenances after placement and compaction of road base:
   (A)   Preliminary punch list;
   (B)   Preliminary air test;
   (C)   Mandrel test;
   (D)   Installation of curb, gutter, sidewalk and other surface features;
   (E)   Official air test;
   (F)   Clean entire sewer system;
   (G)   CCTV inspection;
   (H)   Paving. Coordinate with District Engineer on timing for final pavement lift; and
   (I)   Final punch list.
(Ord. 2019-02, passed 4-25-2019)