(A) (1) Submittal requirements for District plan check for private laterals prior to approval of plans are shown in divisions (B)(1), (B)(2), (B)(3) and (B)(4) below.
(2) After plan check is completed by the District, one set of the checked plans will be returned to the applicant for revisions and resubmittal of the required number of revised sets.
(3) Plan submittals must have information listed below shown on original reproducible tracings to scale with prints submitted there from. The plan must be drawn to adequate scale, with north arrow, on a large enough sheet (11 inches by 17 inches minimum, 30 inches by 42 inches maximum). The minimum scale will be one inch equals 50 feet unless otherwise authorized by the Engineer.
(4) Name, address, telephone number and title of the company or person preparing the plan must clearly be shown on the submitted plans.
(5) Any office or field change from final approved construction plans must be re-approved by the District and may require resubmittal of revised plans and digital files.
(B) (1) Site plans. Two copies of site plan must be submitted to the District. The site plan must show (unless otherwise permitted by the Engineer):
(a) Elevations shown on the plans shall be converted and reported in the NAVD 88 datum. Basis of the topography data shall be provided;
(b) Public street and property dimensions;
(c) All existing and proposed buildings labeled with general usage and plotted accurately on-site;
(d) Areas to be paved and those left unpaved clearly marked;
(e) Ground floor and pad elevations of all buildings;
(f) Finish ground elevations at key points and curb elevations of public street;
(g) Existing ground elevations where cover over proposed sewer is to be less than two feet at time of construction;
(h) Existing District manhole number and rim elevation of nearest upstream existing public sanitary sewer manhole in the street drawn to scale or with its distance shown to the site’s nearest downstream property corner and the new sewer connection;
(i) Existing and proposed utilities plotted correctly and labeled;
(j) The proposed sanitary sewer size, material, minimum slope, invert elevation to nearest 0.1 foot at connection to building plumbing;
(k) Structures proposed, such as cleanouts, manholes, grease interceptors and the like, labeled and shown on the plan; and
(l) Plumbing fixture unit count shown for each building.
(2) Floor plans. Two copies of floor plan must be submitted to the District. (Commercial and industrial only) floor plan must show area layout and proposed usage of various areas of building.
(3) Plumbing and/or mechanical plans. Two copies of plumbing and/or mechanical plan must be submitted to the District. (Commercial and industrial only) plumbing and/or mechanical plan must show interior plumbing (building drain) and the fixtures to be served, all properly labeled as to function. Both existing and proposed plumbing fixtures shall be shown and labeled on the plans.
(4) Roof plan. Two copies of roof plan if rooftop HVAC units are proposed (commercial and industrial only). Condensate lines from HVAC, boilers and the like are not permitted to connect to the sanitary sewer system unless such connections have been reviewed and prior approval from the Engineer is granted in writing.
(Ord. 2019-02, passed 4-25-2019)