Section 9-4095 Certificate of occupancy required.
   (a)   A certificate of occupancy issued by the Administrator is required in advance of:
   (1)   Occupancy or use of a building hereafter erected, altered or moved;
   (2)   A change of use of any building or land; and
   (3)   In addition, a certificate of occupancy shall be required for each monitoring use created by the passage of, and subsequent amendments to, this chapter. The owner of such nonconforming use shall obtain a certificate of occupancy within 30 days of the date of the passage or amendments.
   (b)   A certificate of occupancy, either for the whole or a part of a building shall be applied for coincident with the application for a building permit and shall be issued within 10 days after the erection or structural alterations of such building, or part, shall have been completed in conformity with the provisions of this chapter. A certificate of occupancy shall not be issued unless the proposed use of a building or land conforms to the applicable provisions of this chapter. If the certificate of occupancy is denied, the Administrator shall state in writing the reasons for refusal, and the applicant shall be notified of the refusal. A record of all certificates shall be kept on file in the office of the Administrator, and copies shall be furnished, on request, to any person having a proprietary or tenancy interest in the building or land involved.
(As Amended by Ord. of 6/24/21)