4-4-6: DEMOLITION INSPECTIONS:
   (A)   Inspections Required: The director shall cause an inspection to be made of all demolitions upon the completion of work and at such other stages of work as he may determine to be necessary.
   (B)   Notification For Inspection: The person carrying out a demolition shall notify the director that the site is ready for final inspection. The director shall cause an inspection within twenty four (24) hours of such notification, nonworking days excluded.
   (C)   Discontinuance Of Demolition For Safety Reasons: If, after inspection, the director finds continued demolition will create a hazard to the public, he shall order demolition discontinued and recommend a safer method of demolition to be used. (Ord. 1923, 3-4-2008)