933.18 APPLICATION PROCEDURES FOR POST-CONSTRUCTION STOR WATER MANAGEMENT PLANS.
   (a)    This plan will be combined with the Soil Erosion and Sediment Control, Storm Water Management, Riparian Setback and Wetland Setback Plans that have also been developed for the site.
   
   (b)    Plans developed by the site owners and approved by the Community in accordance with this regulation do not relieve the site owner of responsibility for obtaining all other necessary permits and/or approvals from federal, state, county, and local agencies and departments. lf requirements vary, the most stringent requirement shall be followed.
      If the Community will be requiring that the local soil and water conservation district (SWCD) review the Post-Construction Water Quality Plans the Community should first discuss the issue and how to implement the SWCD plan reviews with the local SWCD.
   (c)   The site owner shall submit a report from the local county soil and water conservation district, which reviews the owner's development, plans and improvement plans. The applicant or his or her designated representative will pay any costs associated with obtaining the report(s) from the local county SWCD. A letter or report from the local County SWCD, and shall approve or return these with comments and recommendations for revisions, within thirty (30) working days after receipt of the plans as described above. A plan rejected because of deficiencies shall receive a report stating specific problems and the procedures for filing a revised plan. At the time of receipt of a revised plan another thirty (30) day review period shall begin.
   (d)   Plans submitted to the City Engineer for review and approval shall be accompanied by other required permits and documentation relevant to the project, including but not limited to the US Army Corps of Engineers, Ohio EPA, ODNR Division of Water and Ohio EPA NPDES Permit for Construction Activities.
   (e)   Five (5) sets of the plans and necessary data required by this regulation shall be submitted to the City Engineer as follows:
      (1)   Format:
         A.   Text material will be on 8.5 by 11 inch paper.
         B.   Drawings will be on paper sized no larger than 24 inch by 36 inches.
         C.   An electronic copy of the drawings and plan shall be submitted in PDF format as directed by the City.
   (f)   The City Engineer shall review the plans, including the approval report from the local county SWCD, and shall approve or return these with comment and recommendations for revisions, within thirty (30) working days after receipt of the plan as described above. A plan rejected because of deficiencies shall receive a report stating specific problems and the procedures for filing revised plan. At the time of receipt of a revised plan another thirty (30) day review period shall begin.
      (1)   Approved plans shall remain valid for two (2) years from the date of approval. After two (2) years the plan(s) approval automatically expires.
      (2)    No soil-disturbing activity shall begin before all necessary local county, state and federal permits have been granted to the owner or operator.
      (3)   The Community will do construction inspections until the site is stabilized as determined by the City Engineer. The construction will not be considered completed until the City Engineer has conducted the Post Construction inspections.
         (Ord. 2021-15. Passed 3-17-21.)