All fees are due at the time of application, unless otherwise specified, and are non-refundable. Project started before obtaining a permit are subject to being charged double the regular fee.
I. ZONING PERMIT.
(A) For new construction or additions.
(1) Residential and agricultural
.
(a) Single-family (including mobile and manufactured): $50 per unit;
(b) Two family, multi-family: $100 per
; and
(c) Accessory
: $50 per unit.
(2) Non-residential or mixed use
.
(a) Up to 20,000 square feet of
: $100;
(b) Over 20,000 square feet of
: $250; and
(c) Accessory
: $100 per unit.
(B) Commercial change in use or occupancy: $75.
(C)
: $100 per
type.
(D)
:
(1) Above ground pool: $50 per pool; and
(2) In-ground pool: $50 per pool plus applicable
.
(E)
: $50.
(F) Off-street parking and loading areas:
(1) Zero to 5,000 square feet: $50; and
(2) Five dollars per 1,000 square feet over 5,000 square feet.
(G)
: $50.
(H) Zoning verification letter: $80.
II. BUILDING PERMIT FEES.
(A) One- and
: new construction. $0.15 per square foot of exterior dimensions (inclusive of living area, garage,
, deck, patios, and porches).
(B)
and non-residential: new construction.
Gross square footage of all levels.
(1) Less than 10,000 square feet: $0.15 per square foot of all floor areas;
(2) 10,000 to 30,000 square feet $0.12 per square foot; and
(3) Over 30,000 square feet: $0.08 per square foot.
(C) Miscellaneous construction. Additions or remodeling of existing
, cell towers or fire alarm systems, decks, accessory
,
, retaining walls, in-ground pools, etc. Co-locations are included in this category.
Construction value | Fee |
Construction value | Fee |
$0 to $500 | $30 |
$501 to $1,000 | $35 |
$1,001 to $2,000 | $40 |
$2,001 to $3,000 | $45 |
$3,001 to $4,000 | $50 |
$4,001 to $5,000 | $55 |
$5,001 to $6,000 | $60 |
$6,001 to $7,000 | $65 |
$7,001 to $8,000 | $70 |
$8,001 to $9,000 | $75 |
$9,001 to $10,000 | $80 |
$10,001 to $11,000 | $85 |
$11,001 to $12,000 | $90 |
$12,001 to $13,000 | $95 |
$13,001 to $14,000 | $100 |
$14,001 to $15,000 | $105 |
$15,001 to $16,000 | $110 |
$16,001 to $17,000 | $115 |
$17,001 to $18,000 | $120 |
$18,001 to $19,000 | $125 |
$19,001 to $20,000 | $130 |
$20,001 to $21,000 | $135 |
$21,001 to $22,000 | $140 |
$22,001 to $23,000 | $145 |
$23,001 to $24,000 | $150 |
$24,001 to $25,000 | $155 |
$25,001 to $50,000 | $160 + $4 per $1,000 valuation or fraction thereof > 25,000 |
$50,001 to $75,000 | $265 + $3 per $1,000 valuation or fraction thereof > 50,000 |
$75,001 to $100,000 | $345 + $2 per $1,000 valuation or fraction thereof > 75,000 |
$100,001 and over | $400 + $2 per $1,000 valuation or fraction thereof > 100,000 |
(D) HVAC systems: See Appendix A attached to this ordinance, as it may be amended from time to time, for HVAC permit fees and HVAC violation fees.
(E) Electric: $30 per unit.
(1) All electric inspections must be conducted by a state licensed and certified electrical inspector.
(2) See Appendix B attached to this ordinance for fees.
(F) Encroachment for city or county road: $50.
(G) Demolition:
(1) Single- and
(including accessory
): $100; and
(2) Multi-family, non-residential or mixed use
: $200.
(H) Fire alarm system:
(1) Zero to 20,000 square feet: $200; and
(2) Each additional 10,000 square feet over 20,000 square feet: $25.
(I) Automatic fire suppression (sprinkler) system:
(1) Less than 20 sprinkler heads: $100;
(2) 21 to 300 sprinkler heads: $200; and
(3) Over 300 sprinkler heads: $200 plus $0.20 per sprinkler head over 300 heads.
(J) Commercial range hoods:
(1) Range hood: $125;
(2) Range hood extinguishing system: $125.
(K) All other suppression systems: $150.
(L) Re-inspection: $100 paid in advance of inspection, applied by the Chief Building Official for third inspection of same failed type.
(M)
code appeal: $400 per item appealed + $150 for administrative fees.
III. LAND DIVISION AND/OR SITE DEVELOPMENT PLAN REVIEW.
(A) Conveyance/identification plat: $250 per
reviewed.
(B) Preliminary site development or Stage 1 plans: Land area by density/use (see chart) + $10 per
/
+ $30 administrative fee.
Single-family detached with less than or equal to 20 acres, and less than or equal to 50 units | $700 |
Single-family detached with over 20 acres, or over 50 units, single- family attached or multi | $800 |
Non-residential or mixed use | $900 |
(C) Improvement plan or Stage 2 plans: Land area by density/use (see chart) + $10 per
/
+ $30 administrative fee.
Single-family detached with less than or equal to 20 acres, and less than or equal to 50 units | $500 |
Single-family detached with over 20 acres, or over 50 units, single- family attached or multi | $700 |
Non-residential or mixed use | $800 |
(D) Supporting plan: $250 per plan when submitted separately.
Note: For accuracy and efficiency, supporting plans, such as landscape, lighting, traffic, geotechnical plans, etc. should be submitted with preliminary/Stage l or improvement/Stage 2 plans.
(E) Grading plan when submitted separately (not included in preliminary or improvement plan review): land area (see chart)
Engineered wall on single-family | $200 |
Sites of three acres or less | $500 |
Sites more than three and less than ten acres | $600 |
Sites more than ten and less than 20 acres | $700 |
Sites more than 20 acres | $800 |
(F) Public improvement inspections:
Street | $2.50 per lineal foot |
Sidewalk (non- residential or mixed use) | $0.10 per lineal foot |
De-attached residential | $100 per |
Attached residential | $50 per unit |
Non-residential or mixed use | $150 per
plus $60 per additional apron above one |
(G)
site plan: $2,500.
(H) Distributed antenna system site plan:
One to three locations | $500 per location |
Four to six locations | $400 per location |
Seven to ten locations | $2,500 |
IV. ZONING REVIEW, MODIFICATION OR APPEAL.
Administrative fees may be combined for multiple requests when the completed application is made at the same time.
(A) Waiver: $400 (per request) + $150 for administrative fees.
(B) Variance.
(1) Agricultural and residential
: $350 + $150 for administrative fees; and
(2) Non-residential or mixed use
: $600 + $150 for administrative fees.
(C)
.
(1) Agricultural and residential
: $400 + $150 for administrative fees; and
(2) Non-residential or mixed use
: $700 + $150 for administrative fees.
(D) Change of nonconforming to another use.
(1) Agricultural and residential
: $250 + $150 for administrative fees; and
(2) Non-residential or mixed use
: $500 + $150 for administrative fees.
(E)
map amendment.
(1) Residential and agricultural
: $1,000 + $10 per acre + $150 for administrative fees;
(2) Commercial
(NC, HC, NSC, SC, RC, PO, PUD, and MLU): $1,200 + $10 per acre + $150 for administrative fees; and
(3) Industrial
(1-1,1-2, IM, I-4, and I-5): $1,500 + $10 per acre + $150 for administrative fees.
(F)
text (ordinance) or
regulation amendment. (Requires sponsorship by
or local legislative body): $1,500 + $250 for publication, recording and administrative fees.
(G) Appeals.
(1) Agricultural and residential
: $350 + $150 for administrative fees;
(2) Other non-residential or mixed use
: $650 + $150 for administrative fees.
V. MISCELLANEOUS.
(A) Extension of time (requested by applicant) for review, work to begin, or inspection: $200.
(B) Revision, resubmission or change of approved site plans: 80% of original fee.
(C) Postponement or continuance of meeting/hearing, as a result of the applicant's action: $150 for administrative fees.
(D) Scan, plot, and reproduction.
(1) Oversize scan: $10 per sheet;
(2) Oversize plot:
(a) Black and white: $5; and
(b) Color: $10.
(3) Copy:
(a) Letter or legal size - black and white: $0.15 per copy;
(b) Letter or legal size - color: $0.25 per copy;
(c) Ledger (11x17) size - black and white: $0.50 per copy; and
(d) Ledger (11 x 17) size - color: $1 per copy.
(2) Planning documents:
(a) Zoning ordinance,
regulations or
(paper): $30 per binder;
(b)
(CD): $5; and
(c) Combo package:
(paper and CD), zoning ordinance, and
regulations: $90.
(E) Custom planning services: $80 per hour.
(F) Custom mapping services: $45 per hour.
(G) Bank fees (including use of credit or debit card): charges imposed by bank.
(Ord. O-06-16, passed 6-15-16; Am. Ord. O-12-23, passed 9-20-23)