§ 152.40 GENERAL STANDARDS.
   (A)   Reasonably safe from flooding. Review all permit application to determine whether proposed building sites will be reasonably safe from flooding.
   (B)   Anchoring. All new construction and substantial improvements shall be anchored to prevent flotation, collapse, and lateral movement of the structure.
   (C)   Flood resistant materials and equipment. All new construction and substantial improvements shall be constructed with flood resistant materials and utility equipment resistant to flood damage in accordance with Technical Bulletin 2, Flood Damage-Resistant Materials Requirements, dated 8/08, and available from the Federal Emergency Management Agency.
   (D)   Minimize flood damage. All new construction and substantial improvements shall be constructed by methods and practices that minimize flood damages.
   (E)   Critical development. Shall be elevated to 500 year flood elevation or be elevated to the highest known historical flood elevation (where records are available), whichever is greater. If no data exists establishing the 500 year flood elevation or the highest known historical flood elevation, the applicant shall provide a hydrologic and hydraulic engineering analysis that generates 500 year flood elevation data.
   (F)   Utilities. Electrical, ventilation, plumbing, heating and air conditioning equipment (including ductwork), and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of the base flood plus one foot (freeboard).
   (G)   Water supply systems. All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system.
   (H)   Sanitary sewage systems. New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharges from the systems into floodwaters. On-site waste disposal systems shall be located and constructed to avoid impairment to them or contamination from them during flooding.
   (I)   Gas or liquid storage tanks. All gas or liquid storage tanks, either located above ground or buried, shall be anchored to prevent flotation and lateral movement resulting from hydrodynamic and hydrostatic loads.
   (J)   Alteration, repair, reconstruction, or improvements. Any alteration, repair, reconstruction, or improvement to a structure that is in compliance with the provisions of this chapter, shall meet the requirements of "new construction" as contained in this chapter. This includes post-FIRM development and structures.
   (K)   Non-conforming buildings or uses. Non-conforming buildings or uses may not be enlarged, replaced, or rebuilt unless such enlargement or reconstruction is accomplished in conformance with the provisions of this chapter. Provided, however, nothing in this chapter shall prevent the repair, reconstruction, or replacement of an existing building or structure located totally or partially within the floodway, provided that the bulk of the building or structure below base flood elevation in the floodway is not increased and provided that such repair, reconstruction, or replacement meets all of the other requirements of this chapter.
   (L)   Americans with Disabilities Act (ADA). A building must meet the specific standards for floodplain construction, as well as any applicable ADA requirements. The ADA is not justification for issuing a variance or otherwise waiving these requirements. Also, the cost of improvements required to meet the ADA provisions shall be included in the cost of the improvements for calculating substantial improvement.
(Ord. 14-006, passed 2-25-14; Am. Ord. 2018-012, passed 8-28-18)