Loading...
12-15-03: DEFINITIONS:
Unless specifically defined in this section, words or phrases used in this article shall be interpreted according to the meaning they have in common usage.
   ACCESSORY STRUCTURE (APPURTENANT STRUCTURE): A structure on the same lot or parcel as a principal structure, the use of which is incidental and subordinate to the principal structure.
   ADDITION (To An Existing Building): An extension or increase in the floor area or height of a building or structure.
   APPEAL: A request for review of the Floodplain Administrator's interpretation of provisions of this article or request for a variance.
   AREA OF SHALLOW FLOODING: A designated AO, AH, AR/AO, or AR/AH Zone on a community's Flood Insurance Rate Map (FIRM) with a one percent (1%) or greater annual chance of flooding to an average depth of one foot (1') to three feet (3') where a clearly defined channel does not exist, where the path of flooding is unpredictable, and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow.
   AREA OF SPECIAL FLOOD HAZARD: See definition of special flood hazard area (SFHA).
   BASE FLOOD: The flood having a one percent (1%) chance of being equaled or exceeded in any given year.
   BASE FLOOD ELEVATION (BFE): A determination by the Federal Insurance Administrator of the water surface elevations of the base flood, that is, the flood level that has a one percent (1%) or greater chance of occurrence in any given year. When the BFE has not been provided in a special flood hazard area, it may be obtained from engineering studies available from a Federal, State, or other source using FEMA-approved engineering methodologies. This elevation, when combined with the freeboard, establishes the flood protection elevation.
   BASEMENT: The area of a building having its floor subgrade (below ground level) on all sides.
   BUILDING: See definition of structure.
   CRITICAL FACILITY: Facilities that are vital to flood response activities or critical to the health and safety of the public before, during, and after a flood, such as a hospital, emergency operations center, electric substation, police station, fire station, nursing home, school, vehicle and equipment storage facility, or shelter; and facilities that, if flooded, would make the flood problem and its impacts much worse, such as a hazardous materials facility, power generation facility, water utility, or wastewater treatment plant.
   DATUM: The vertical datum is a base measurement point (or set of points) from which all elevations are determined. Historically, that common set of points has been the National Geodetic Vertical Datum of 1929 (NGVD29). The vertical datum currently adopted by the Federal government as a basis for measuring heights is the North American Vertical Datum of 1988 (NAVD88).
   DEVELOPMENT: Any manmade change to improved or unimproved real estate, including, but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials.
   DEVELOPMENT ACTIVITY: Any activity defined as development which will necessitate a floodplain development permit; such as: the construction of buildings, structures, or accessory structures; additions or substantial improvements to existing structures; bulkheads, retaining walls, piers, and pools; the placement of mobile homes; or the deposition or extraction of materials; the construction or elevation of dikes, berms and levees.
   DIGITAL FLOOD INSURANCE RATE MAP (DFIRM): The digital official map of a community, issued by the Federal Insurance Administrator, on which both the special flood hazard areas and the risk premium zones applicable to the community are delineated.
   ELEVATED BUILDING: For insurance purposes, a non-basement building which has its lowest elevated floor raised above ground level by foundation walls, shear walls, posts, piers, pilings, or columns.
   ELEVATION CERTIFICATE: The Elevation Certificate is an important administrative tool of the NFIP. It is used to determine the proper flood insurance premium rate; it is used to document elevation information; and it may be used to support a request for a Letter of Map Amendment (LOMA) or Letter of Map Revision Based On Fill (LOMR-F).
   ENCLOSURE: An area enclosed by solid walls below the BFE/FPE or an area formed when any space below the BFE/FPE is enclosed on all sides by walls or partitions. Insect screening or open wood lattice used to surround space below the BFE/FPE is not considered an enclosure.
   ENCROACHMENT: The advance or infringement of uses, fill, excavation, buildings, structures, or development into a floodplain, which may impede or alter the flow capacity of a floodplain.
   EXISTING CONSTRUCTION: For the purposes of determining rates, structures for which the "start of construction" commenced before the effective date of the FIRM or before January 1, 1975, for FIRMs effective before that date. "Existing construction" may also be referred to as "existing structures".
   EXISTING MANUFACTURED HOME PARK OR MANUFACTURED HOME SUBDIVISION: A manufactured home park or subdivision where the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and final site grading or the pouring of concrete pads) is completed before the effective date of the original floodplain management regulations adopted by the community May 2, 1975.
   EXISTING STRUCTURES: See definition of existing construction.
   EXPANSION TO AN EXISTING MANUFACTURED HOME PARK OR SUBDIVISION: The preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads).
   FLOOD BOUNDARY AND FLOODWAY MAP (FBFM): The FBFM shows how the floodplain is divided into the floodway and flood fringe where streams are studied in detail. They also show general floodplain areas where floodplains have been studied by approximate methods. (Old format pre 1986.)
   FLOOD ELEVATION DETERMINATION: See definition of base flood elevation (BFE).
   FLOOD ELEVATION STUDY: See definition of Flood Insurance Study (FIS).
   FLOOD HAZARD BOUNDARY MAP (FHBM): An official map of the City, issued by the Federal Insurance Administrator, where the boundaries of the flood, mudslide (i.e., mudflow) related erosion areas having special hazards have been designated as Zones A, M, and/or E.
   FLOOD INSURANCE RATE MAP (FIRM): An official map of the community, issued by the Federal Insurance Administration, delineating the areas of special flood hazard and/or risk premium zones applicable to the community. A FIRM that has been made available digitally is called a Digital Flood Insurance Rate Map (DFIRM).
   FLOOD INSURANCE STUDY (FIS): An examination, evaluation, and determination of flood hazards and, if appropriate, corresponding water surface elevations; or an examination, evaluation and determination of mudslide (i.e., mudflow) and/or flood-related erosion hazards.
   FLOOD OR FLOODING: (1) A general and temporary condition of partial or complete inundation of normally dry land areas from:
      A. The overflow of inland waters;
      B. The unusual and rapid accumulation or runoff of surface waters from any source;
      C. Mudslides (i.e., mudflows) which are proximately caused by flooding as defined in subsection (1)B of this definition and are akin to a river of liquid and flowing mud on the surfaces of normally dry land areas, as when earth is carried by a current of water and deposited along the path of the current.
   (2)   The collapse or subsidence of land along the shore of a lake or other body of water as a result of erosion or undermining caused by waves or currents of water exceeding anticipated cyclical levels or suddenly caused by an unusually high water level in a natural body of water, accompanied by a severe storm, or by an unanticipated force of nature, such as flash flood or an abnormal tidal surge, or by some similarly unusual and unforeseeable event which results in flooding as defined in subsection (1)A of this definition.
   FLOOD PROTECTION ELEVATION (FPE): The base flood elevation plus the freeboard.
   (1)   In "special flood hazard areas" where base flood elevation (BFEs) have been determined, this elevation shall be the BFE plus one foot (1') of freeboard; and
   (2)   In "special flood hazard areas" where no BFE has been established, this elevation shall be at least two feet (2') above the highest adjacent grade.
   FLOOD PROTECTION SYSTEM: Those physical structural works for which funds have been authorized, appropriated, and expended and which have been constructed specifically to modify flooding in order to reduce the extent of the area within a community subject to a "special flood hazard" and the extent of the depths of associated flooding. Such a system typically includes dams, reservoirs, levees, or dikes. These specialized flood modifying works are those constructed in conformance with sound engineering standards.
   FLOOD ZONE: A geographical area shown on a Flood Hazard Boundary Map (FHBM) or Flood Insurance Rate Map (FIRM) that reflects the severity or type of flooding in the area, and applicable insurance rate.
   FLOODPLAIN ADMINISTRATOR: The individual appointed to administer and enforce the floodplain management regulations.
   FLOODPLAIN DEVELOPMENT PERMIT: Any type of permit that is required in conformance with the provisions of this article, prior to the commencement of any development activity.
   FLOODPLAIN MANAGEMENT: The operation of an overall program of corrective and preventative measures for reducing flood damage, including but not limited to emergency preparedness plans, flood control works, and floodplain management regulations.
   FLOODPLAIN MANAGEMENT REGULATIONS: Zoning Ordinances, subdivision regulations, Building Codes, health regulations, special purpose ordinances (such as a Floodplain Ordinance, Grading Ordinance, and Erosion Control Ordinance), and other applications of police power. The term describes such State or local regulations, in any combination thereof, which provide standards for the purpose of flood damage prevention and reduction.
   FLOODPLAIN OR FLOOD PRONE AREA: Any land area susceptible to being inundated by water from any source (see definition of "flooding").
   FLOODPROOFING: Any combination of structural and nonstructural additions, changes, or adjustments to structures which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.
   FLOODWAY: The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than a designated height.
   FREEBOARD: A factor of safety usually expressed in feet above a flood level for the purposes of floodplain management. Freeboard tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, obstructed bridge openings, debris and ice jams and the hydrologic effects of urbanization in a watershed. The base flood elevation (BFE) plus the freeboard establishes the flood protection elevation (FPE). Freeboard shall be one foot (1').
   FUNCTIONALLY DEPENDENT USE: A facility that cannot be used for its intended purpose unless it is located or carried out in close proximity to water, such as a docking or port facility necessary for the loading and unloading of cargo or passengers, shipbuilding, or ship repair facilities. The term does not include long term storage, manufacture, sales, or service facilities.
   HIGHEST ADJACENT GRADE (HAG): The highest natural elevation of the ground surface prior to construction, adjacent to the proposed walls of a structure. Refer to the FEMA Elevation Certificate for HAG related to building elevation information.
   HISTORIC STRUCTURE: A structure that is:
   (1)   Listed individually in the National Register of Historic Places (a listing maintained by the U.S. Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register.
   (2)   Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or to a district preliminarily determined by the Secretary to qualify as a registered historic district.
   (3)   Individually listed on a State Inventory of Historic Places and determined as eligible by states with historic preservation programs which have been approved by the Secretary of the Interior, or
   (4)   Individually listed on a Local Inventory of Historic Places and determined as eligible by communities with historic preservation programs that have been certified either:
      A. By an approved State program as determined by the Secretary of the Interior, or
      B. Directly by the Secretary of the Interior in states without approved programs.
   LETTER OF MAP CHANGE (LOMC): A general term used to refer to the several types of revisions and amendments to FIRMs that can be accomplished by letter. They include Letter of Map Amendment (LOMA), Letter of Map Revision (LOMR), and Letter of Map Revision Based On Fill (LOMR-F).
      Conditional Letter Of Map Revision (CLOMR): A formal review and comment as to whether a proposed flood protection project or other project complies with the minimum NFIP requirements for such projects with respect to delineation of special flood hazard areas. A CLOMR does not revise the effective Flood Insurance Rate Map (FIRM) or Flood Insurance Study (FIS). Upon submission and approval of certified as-built documentation, a Letter of Map Revision (LOMR) may be issued by FEMA to revise the effective FIRM. Building permits and/or flood development permits cannot be issued based on a CLOMR, because a CLOMR does not change the NFIP map.
      Letter Of Map Amendment (LOMA): An official amendment, by letter, to an effective National Flood Insurance Program (NFIP) map. A LOMA establishes a property's or structure's location in relation to the special flood hazard area (SFHA). LOMAs are usually issued because a property or structure has been inadvertently mapped as being in the floodplain but is actually on natural high ground above the base flood elevation.
      Letter Of Map Revision (LOMR):   FEMA's modification to an effective Flood Insurance Rate Map (FIRM) or a Flood Boundary and Floodway Map (FBFM) or both. LOMRs are generally based on the implementation of physical measures that affect the hydrologic or hydraulic characteristics of a flooding source and thus result in the modification of the existing regulatory floodway, the effective base flood elevations (BFEs), or the special flood hazard area (SFHA). The LOMR officially revises the Flood Insurance Rate Map (FIRM) or Flood Boundary and Floodway Map (FBFM), and sometimes the Flood Insurance Study (FIS) report, and when appropriate, includes a description of the modifications. The LOMR is generally accompanied by an annotated copy of the affected portions of the FIRM, FBFM, or FIS report.
      Letter Of Map Revision Based On Fill (LOMR-F):   FEMA's modification of the special flood hazard area (SFHA) shown on the Flood Insurance Rate Map (FIRM) based on the placement of fill outside the existing regulatory floodway. The LOMR-F does not change the FIRM, FBFM, or FIS report.
   LEVEE: A manmade structure, usually an earthen embankment, designed and constructed according to sound engineering practices, to contain, control, or divert the flow of water so as to provide protection from temporary flooding.
   LEVEE SYSTEM: A flood protection system that consists of a levee, or levees, and associated structures, such as closure and drainage devices, which are constructed and operated in accordance with sound engineering practices.
   LOWEST ADJACENT GRADE (LAG): The lowest point of the ground level next to the structure. Refer to the FEMA Elevation Certificate for LAG related to building elevation information.
   LOWEST FLOOR: The lowest floor of the lowest enclosed area (including basement). An unfinished or flood resistant enclosure, used solely for parking of vehicles, building access, or storage, in an area other than a basement, is not considered a building's lowest floor; provided, that such enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirements of 44 CFR section 60.3 and this article.
   MANUFACTURED HOME: A structure, transportable in one or more sections, built on a permanent chassis and designed to be used with or without a permanent foundation when connected to the required utilities. The term "manufactured home" does not include a "recreational vehicle".
   MANUFACTURED HOME PARK OR SUBDIVISION: A parcel (or contiguous parcels) of land divided into two (2) or more manufactured home lots for rent or sale.
   MARKET VALUE: The building value, not including the land value and that of any accessory structures or other improvements on the lot. Market value may be established by independent certified appraisal; replacement cost depreciated for age of building and quality of construction (actual cash value); or adjusted tax assessed values.
   MEAN SEA LEVEL: For purposes of the national flood insurance program, the National Geodetic Vertical Datum (NGVD) of 1929 or other datum, to which base flood elevations shown on the City's FIRM are referenced.
   MUDSLIDE (i.e., MUDFLOW): Describes a condition where there is a river, flow, or inundation of liquid mud down a hillside usually as a result of a dual condition of loss of brush cover, and the subsequent accumulation of water on the ground preceded by a period of unusually heavy or sustained rain. A mudslide (i.e., mudflow) may occur as a distinct phenomenon while a landslide is in progress, and will be recognized as such by the Administrator only if the mudflow, and not the landslide, is the proximate cause of damage that occurs.
   MUDSLIDE (i.e., MUDFLOW) AREA MANAGEMENT: The operation of an overall program of corrective and preventive measures for reducing mudslide (i.e., mudflow) damage, including but not limited to emergency preparedness plans, mudslide control works, and floodplain management regulations.
   MUDSLIDE (i.e., MUDFLOW) PRONE AREA: An area with land surfaces and slopes of unconsolidated material where the history, geology, and climate indicate a potential for mudflow.
   NATIONAL FLOOD INSURANCE PROGRAM (NFIP): The NFIP is a Federal program created by Congress to mitigate future flood losses nationwide through sound, community-enforced Building and Zoning Ordinances and to provide access to affordable, Federally backed flood insurance protection for property owners.
   NEW CONSTRUCTION: For floodplain management purposes, a structure for which the start of construction commenced on or after the effective date of a floodplain management regulation adopted by a community and includes any subsequent improvements to such structures. Any construction started after May 2, 1975 and before the effective start date of this article is subject to the ordinance in effect at the time the permit was issued, provided the start of construction was within one hundred eighty (180) days of permit issuance.
   NEW MANUFACTURED HOME PARK OR SUBDIVISION: A place where the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and final site grading or the pouring of concrete pads) is completed on or after the effective date of floodplain management regulations adopted by a community May 2, 1975.
   POST-FIRM: Construction or other development for which the "start of construction" occurred on or after the effective date of the initial Flood Insurance Rate Map (FIRM).
   PRE-FIRM: Construction or other development for which the "start of construction" occurred before September 3, 1980, the effective date of the initial Flood Insurance Rate Map (FIRM).
   RECREATIONAL VEHICLE: A vehicle that is:
   (1)   Built on a single chassis,
   (2)   Four hundred (400) square feet or less when measured at the largest horizontal projection,
   (3)   Designed to be self-propelled or permanently towed by a light duty truck, and
   (4)   Designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
   REGULATORY FLOODWAY: See definition of floodway.
   REMEDY A VIOLATION: To bring the structure or other development into compliance with State or local floodplain management regulations, or, if this is not possible, to reduce the impacts of its non-compliance. Ways that impacts may be reduced include protecting the structure or other affected development from flood damages, implementing the enforcement provisions of this article or otherwise deterring future similar violations, or reducing Federal financial exposure with regard to the structure or other development.
   REPETITIVE LOSS STRUCTURE: An NFIP-insured structure that has had at least two (2) paid flood losses of more than one thousand dollars ($1,000.00) each in any 10-year period since 1978.
   RIVERINE: Relating to, formed by, or resembling a river (including tributaries), stream, brook, etc.
   SPECIAL FLOOD HAZARD AREA (SFHA): The land in the floodplain within a community subject to a one percent (1%) or greater chance of flooding in any given year. For purposes of these regulations, the term "special flood hazard area" is synonymous in meaning with the phrase "area of special flood hazard".
   START OF CONSTRUCTION: Includes substantial improvement and means the date the development permit was issued, provided the actual start of construction, repair, reconstruction, or improvement was within one hundred eighty (180) days of the permit date. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading, and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not the alteration affects the external dimensions of a building.
   STRUCTURE: A walled and roofed building, including a gas or liquid storage tank that is principally aboveground, as well as a manufactured home.
   SUBSTANTIAL DAMAGE: Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed fifty percent (50%) of its market value before the damage occurred. See definition of "substantial improvement". For insurance purposes, substantial damage also means flood-related damage sustained by a structure on two (2) separate occasions during a 10-year period for which the cost of repairs at the time of each such flood event, on the average, equals or exceeds twenty-five percent (25%) of the market value of the structure before the damage occurred.
   SUBSTANTIAL IMPROVEMENT: Reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds fifty percent (50%) of the market value of the structure before the "start of construction" of the improvement. This term includes structures which have incurred "substantial damage", regardless of the actual repair work performed. The term does not include either:
   (1)   Any project for improvement of a structure to correct existing violations of State or local Health, Sanitary, or Safety Code specifications, which have been identified by the local Code enforcement official and which are the minimum necessary to assure safe living conditions, or
   (2)   Any alteration of a "historic structure", provided that the alteration will not preclude the structure's continued designation as a "historic structure", and the alteration is approved by variance issued pursuant to this article.
   TECHNICAL BULLETINS AND TECHNICAL FACT SHEETS:   FEMA publications that provide guidance concerning the building performance standards of the NFIP, which are contained in title 44 of the U.S. Code of Federal Regulations section 60.3. The bulletins and fact sheets are intended for use primarily by State and local officials responsible for interpreting and enforcing NFIP regulations and by members of the development community, such as design professionals and builders. New bulletins, as well as updates of existing bulletins, are issued periodically as needed. The bulletins do not create regulations. Rather they provide specific guidance for complying with the minimum requirements of existing NFIP regulations.
It should be noted that Technical Bulletins and Technical Fact Sheets provide guidance on the minimum requirements of the NFIP regulations. State or community requirements that exceed those of the NFIP take precedence. Design professionals should contact the community officials to determine whether more restrictive State or local regulations apply to the building or site in question. All applicable standards of the State or local Building Code must also be met for any building in a flood hazard area.
   TEMPERATURE CONTROLLED: Having the temperature regulated by a heating and/or cooling system, built-in or appliance.
   VARIANCE: A grant of relief by the Governing Body from a requirement of this article.
   VIOLATION: The failure of a structure or other development to be fully compliant with the community's floodplain management regulations. A structure or other development without the Finished Construction Elevation Certificate, other certifications, or other evidence of compliance required in 44 CFR section 60.3(b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5) is presumed to be in violation until such time as that documentation is provided.
   WATER SURFACE ELEVATION: The height, in relation to the National Geodetic Vertical Datum (NGVD) of 1929 or the North American Vertical Datum (NAVD) of 1988 (or other specified datum) of floods of various magnitudes and frequencies in the floodplains of coastal or riverine areas.
   WATERCOURSE: For the purposes of this article only, a lake, river, creek, stream, wash, channel, or other topographic feature within a flood hazard area in which water regularly flows or is known to experience frequent non-anthropogenic flooding. (Ord. 2875, 5-16-2011, eff. 5-24-2011; Ord. 2923, 4-15-2013; Ord. 3207, 3-4-2019)
12-15-05: GENERAL PROVISIONS:
   (1)   Lands To Which This Article Applies: This article shall apply to all special flood hazard areas within the jurisdiction of the City of Caldwell. Nothing in this article is intended to allow uses or structures that are otherwise prohibited by the Zoning Ordinance. (Ord. 2875, 5-16-2011, eff. 5-24-2011)
   (2)   Basis For Areas Of Special Flood Hazard: The special flood hazard areas identified by the Federal Insurance Administrator in a scientific and engineering report titled "Flood Insurance Study (FIS) for Canyon County, Idaho and Incorporated Areas", dated June 7, 2019, with accompanying Flood Insurance Rate Maps (FIRM) or Digital Flood Insurance Rate Maps (DFIRM), and other supporting data, are adopted by reference and declared a part of this article. The FIS and the FIRM are on file at the Office of the City Engineer at 621 Cleveland Blvd. in Caldwell, Idaho 83605.
   (3)   Establishment Of Floodplain Development Permit: A floodplain development permit shall be required in conformance with the provisions of this article prior to the commencement of any development activities within special flood hazard areas determined in accordance with the provisions of subsection 12-15-07(3) of this article.
   (4)   Compliance: No structure or land shall hereafter be located, extended, converted, altered, or developed in any way without full compliance with the terms of this article and other applicable regulations.
   (5)   Abrogation And Greater Restrictions: This article shall not in any way repeal, abrogate, impair, or remove the necessity of compliance with any other laws, ordinances, regulations, easements, covenants, or deed restrictions, etc. However, where this article and another conflict or overlap, whichever imposes more stringent or greater restrictions shall control.
   (6)   Interpretation: In the interpretation and application of this article all provisions shall be:
      A.   Considered as minimum requirements; and
      B.   Deemed neither to limit nor repeal any other powers granted under State Statutes.
   (7)   Warning And Disclaimer Of Liability: The degree of flood protection required by this article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur. Flood heights may be increased by manmade or natural causes. This article does not imply that land outside the special flood hazard areas or uses permitted within such areas will be free from flooding or flood damages. This article shall not create liability on the part of the City of Caldwell or by any officer or employee thereof for flood damages that result from reliance on this article or an administrative decision lawfully made hereunder.
   (8)   Penalties For Violation: No structure or land shall hereafter be located, extended, converted, or altered unless in full compliance with the terms of this article and other applicable regulations. Pursuant to the powers granted by Idaho Code section 50-302, violation of the provisions of this article or failure to comply with any of its requirements, including violation of conditions and safeguards established in connection with grants of variance or special exceptions, shall constitute a misdemeanor. Any person who violates this article or fails to comply with any of its requirements may, upon conviction thereof, be fined not more than one hundred dollars ($100.00). Each day the violation continues shall constitute a new and separate violation. Nothing herein contained shall prevent the City of Caldwell from taking such other lawful actions as is necessary to prevent or remedy any violation. (Ord. 3207, 3-4-2019)
12-15-07: ADMINISTRATION:
   (1)   Designation Of Floodplain Administrator: The City Engineer or his designee, hereinafter referred to as the "Floodplain Administrator", is hereby appointed to administer and implement the provisions of this article.
   (2)   Duties And Responsibilities Of The Floodplain Administrator: The Floodplain Administrator shall perform, but not be limited to, the following duties:
      A.   Review all floodplain development applications and issue permits for all proposed development within special flood hazard areas to assure that the requirements of this article have been satisfied.
      B.   Review all proposed development within special flood hazard areas to assure that all necessary local, State, and Federal permits have been received, including section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 USC 1334.
      C.   Notify adjacent communities and the Idaho Department of Water Resources State Coordinator for the National Flood Insurance Program (NFIP) prior to any alteration or relocation of a watercourse and submit evidence of such notification to the Federal Insurance Administrator (FIA). (This is the LOMC procedure.)
      D.   Assure that the flood carrying capacity within the altered or relocated portion of any watercourse is maintained. (This is a hydraulic and hydrology analysis.)
      E.   Prevent encroachments into floodways unless the certification and flood hazard reduction provisions of subsection (5) of this section are met.
      F.   Obtain and maintain actual elevation. A person contesting the location of the floodplain elevation boundary shall be given a reasonable opportunity to appeal the interpretation, as provided in this article.
      G.   Review plans to verify public utilities are constructed in accordance with the provisions of subsections 12-15-09(1)E through (1)G of this article.
      H.   When floodproofing is utilized for a particular structure, obtain and maintain certifications from a registered professional engineer or architect in accordance with the provisions of subsection (3)C of this section and subsection 12-15-09(2)B of this article.
      I.   Where interpretation is needed as to the exact location of boundaries of the special flood hazard areas, and floodways (for example, where there appears to be a conflict between a mapped boundary and actual field conditions), make the necessary interpretation. The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this article.
      J.   When base flood elevation (BFE) data has not been provided in accordance with the provisions of subsection 12-15-05(2) of this article, obtain, review, and reasonably utilize any BFE data, along with floodway data available from a Federal, State, or other source, including data developed pursuant to subsection 12-15-09(3)B of this article, in order to administer the provisions of this article.
      K.   When base flood elevation (BFE) data is provided but no floodway data has been provided in accordance with the provisions of subsection 12-15-05(2) of this article, require that no new construction, substantial improvements, or other development (including fill) shall be permitted within Zones A1-30 and AE on the community's FIRM, unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one foot (1') at any point within the community. (This is a hydraulic and hydrology analysis.)
      L.   Permanently maintain all records that pertain to the administration of this article and make these records available for public inspection, recognizing that such information may be subject to the Privacy Act of 1974, as amended.
      M.   Make on-site inspections of work in progress. As the work pursuant to a floodplain development permit progresses, the Floodplain Administrator shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of this article and the terms of the permit. In exercising this power, the Floodplain Administrator has a right, upon presentation of proper credentials, to enter on any premises within the jurisdiction of the community at any reasonable hour for the purposes of inspection or other enforcement action.
      N.   Notify the Department of Building Safety to issue stop-work orders as required. Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this article, the Floodplain Administrator may notify the Building Department to order the work to be immediately stopped. The stop-work order shall be in writing and directed to the person doing or in charge of the work. The stop-work order shall state the specific work to be stopped, the specific reason(s) for the stoppage, and the condition(s) under which the work may be resumed. Violation of a stop-work order shall constitute a violation of this article, and shall be punishable as a violation of this article under subsection 12-15-05(8) of this article.
      O.   Revoke floodplain development permits as required. The Floodplain Administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason(s) for the revocation. Permits shall be revoked for any substantial departure from the approved application, plans, and specifications; for refusal or failure to comply with the requirements of State or local laws; or for false statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable State or local law may also be revoked.
      P.   Make periodic inspections throughout the special flood hazard areas within the jurisdiction of the community. The Floodplain Administrator and each member of his or her Inspections Department shall have a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action.
      Q.   Follow through with corrective procedures of subsection (4) of this section.
      R.   Review, provide input, and make recommendations for variance requests.
      S.   Maintain a current map repository to include, but not limited to, the FIS Report, FIRM and other official flood maps, and studies adopted in accordance with the provisions of subsection 12-15-05(2) of this article, including any revisions thereto including Letters of Map Change, issued by FEMA. Notify the NFIP State Coordinator and FEMA of the community's mapping needs.
      T.   Coordinate revisions to FIS reports and FIRMs, including Letters of Map Revision Based On Fill (LOMR-Fs) and Letters of Map Revision (LOMRs).
      U.   A community's base flood elevations may increase or decrease resulting from physical changes affecting flooding conditions. As soon as practicable, but not later than six (6) months after the date such information becomes available, a community shall notify the Federal Insurance Administrator (FIA) of the changes by submitting technical or scientific data in accordance with this article. Such a submission is necessary so that upon confirmation of those physical changes affecting flooding conditions, risk premium rates and floodplain management requirements will be based upon current data.
      V.   Upon occurrence, notify the Federal Insurance Administrator (FIA) in writing whenever the boundaries of the community have been modified by annexation or the community has otherwise assumed or no longer has authority to adopt and enforce floodplain management regulations for a particular area. In order that all FHBMs and FIRMs accurately represent the community's boundaries, include within such notification a copy of a map of the community suitable for reproduction, clearly delineating the new corporate limits or new area for which the community has assumed or relinquished floodplain management regulatory authority.
   (3)   Floodplain Development Application, Permit, And Certification Requirements:
      A.   Application Requirements: Application for a floodplain development permit shall be made to the Floodplain Administrator prior to any development activities located within special flood hazard areas. All applicable fields on the form shall be filled out completely before submitting it to the Floodplain Administrator to apply for a floodplain development permit.
      B.   Permit Requirements: The floodplain development permit shall, as applicable, include, but not be limited to:
         1.   A complete description of all the development to be permitted under the floodplain development permit (i.e., house, garage, pool, septic, solid wall or barrier, cabana, pole barn, chicken coop, pier, bridge, mining, dredging, filling, rip-rap, dock, grading, paving, excavation or drilling operation, or storage of equipment or material, etc.).
         2.   The special flood hazard area determination for the proposed development in accordance with available data specified in subsection 12-15-05(2) of this article.
         3.   The flood protection elevation required for the lowest floor and all attendant utilities.
         4.   The flood protection elevation required for the protection of all utility equipment and machinery.
         5.   All certification submittal requirements with timelines.
         6.   A statement that no fill material or other development shall encroach into the floodway of any watercourse, as applicable.
         7.   The flood openings requirements.
         8.   Floodplain development permits shall expire if construction does not commence ("start of construction") within one hundred eighty (180) days of permit issuance. If the associated building permit is allowed to expire, revoked, or abandoned, the respective floodplain development permit is also of no further force or effect. Renewal or reinstatement of the permit with the associated building permit requires resubmittal or, at a minimum, written approval from the Floodplain Administrator.
         9.   Fully enclosed areas below the lowest floor are usable solely for parking of vehicles, building access, or storage.
         10.   All materials below BFE must be flood resistant materials.
      C.   Certification Requirements:
         1.   Elevation Certificates:
            (A)   A Construction Drawings Elevation Certificate (FEMA Form 86-0-33) is required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the elevation of the lowest floor, in relation to mean sea level. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder prior to the beginning of construction. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit.
            (B)   A Building Under Construction Elevation Certificate (FEMA Form 86-0-33) may be required by the Floodplain Administrator after the lowest floor is established. Within seven (7) calendar days of establishment of the lowest floor elevation, it shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the elevation of the lowest floor, in relation to mean sea level. Any work done within the seven (7) day calendar period and prior to submission of the certification shall be at the permit holder's risk. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further work being permitted to proceed. Failure to submit the certification or failure to make required corrections shall be cause to issue a stop-work order for the project.
            (C)   A final as-built Finished Construction Elevation Certificate (FEMA Form 86-0-33) is required after construction is completed and prior to Certificate of Compliance/Occupancy issuance. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of final as- built construction of the elevation of the lowest floor and all attendant utilities. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to Certificate of Compliance/Occupancy issuance. In some instances, another certification may be required to certify corrected as-built construction. Failure to submit the certification or failure to make required corrections shall be cause to withhold the issuance of a Certificate of Compliance/Occupancy.
The Finished Construction Elevation Certificate certifier shall provide at least three (3) photographs showing the front, side, and rear of the building taken within ninety (90) days from the date of certification. The photographs must be taken with views confirming the building description and diagram number provided in section A. To the extent possible, these photographs should show the entire building including foundation. If the building has split-level or multi-level areas, provide at least two (2) additional photographs showing side views of the building. In addition, when applicable, provide a photograph of the foundation showing a representative example of the flood openings or vents. All photographs must be in color and measure at least 3" x 3". Digital photographs are acceptable.
         2.   Floodproofing Certificate: If non-residential floodproofing is used to meet the flood protection elevation requirements, design plans, with supporting data, an operational plan, and an inspection and maintenance plan are required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the floodproofed design elevation of the lowest floor and all attendant utilities, in relation to mean sea level. Floodproofing certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same. The Floodplain Administrator shall review the certificate data, the operational plan, and the inspection and maintenance plan. Deficiencies detected by such review shall be corrected by the applicant prior to permit approval. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit. Prior to request for a Certificate of Compliance/Occupancy a Floodproofing Certificate (FEMA Form 086-0-34) shall be provided to the Floodplain Administrator for review and approval.
         3.   Engineered Foundation Certification: If a manufactured home is placed within Zone A, AE, AH, AO, or A1-30 and the elevation of the chassis is more than thirty six inches (36") in height above grade, an engineered foundation certification is required in accordance with the provisions of subsection 12-15-09(2)C2 of this article.
         4.   Altering Or Relocating Watercourse: If a watercourse within a special flood hazard area is to be altered or relocated, the following shall all be submitted by the permit applicant prior to issuance of a floodplain development permit:
            (A)   A description of the extent of watercourse alteration or relocation; and
            (B)   A professional engineer's certified report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream; and
            (C)   A map showing the location of the proposed watercourse alteration or relocation.
         5.   Certification Exemptions: The following structures, are exempt from the elevation/floodproofing certification requirements specified in subsections (3)C1 and (3)C2 of this section.
            (A)   Recreational vehicles meeting requirements of subsection 12-15-09(2)E1 of this article;
            (B)   Temporary structures meeting requirements of subsection 12-15-09(2)F of this article; and
            (C)   Accessory structures less than two hundred (200) square feet meeting requirements of subsection 12-15-09(2)G of this article.
      D.   Determinations For Existing Buildings And Structures: For applications for building permits to improve buildings and structures, including alterations, movement, enlargement, replacement, repair, change of occupancy, additions, rehabilitations, renovations, improvements, repairs of damage, and any other improvement of or work on such buildings and structures, the Floodplain Administrator, in coordination with the building official, shall:
         1.   Estimate the market value, or if reasonably accessible means of determining value cannot be obtained, require the applicant to obtain an appraisal of the market value prepared by a qualified independent appraiser, of the building or structure before the start of construction of the proposed work. In the case of repair, the market value of the building or structure shall be the market value before the damage occurred and before any repairs are made;
         2.   Compare the cost to perform the improvement, the cost to repair a damaged building to its pre-damaged condition, or the combined costs of improvements and repairs, if applicable, to the market value of the building or structure;
         3.   Determine and document whether the proposed work constitutes substantial improvement or repair of substantial damage; and
         4.   Notify the applicant if it is determined that the work constitutes substantial improvement or repair of substantial damage and that compliance with the flood resistant construction requirements of the adopted Idaho Building Code and this article is required.
   (4)   Corrective Procedures:
      A.   Violations To Be Corrected: When the Floodplain Administrator finds violations of applicable State and local laws, it shall be his or her duty to notify the owner or occupant of the building of the violation. The owner or occupant shall remedy each of the violations of law cited in such notification.
      B.   Actions In Event Of Failure To Take Corrective Action: If the owner of a building or property shall fail to take prompt corrective action, the Floodplain Administrator shall give the owner written notice, by certified or registered mail to the owner's last known address or by personal service, stating:
         1.   Violation: That the building or property is in violation of the floodplain management regulations;
         2.   Order To Take Corrective Action: The Floodplain Administrator may issue an order to alter, vacate, or demolish the building; or to remove fill as applicable. Said order shall specify the period of time in which the corrective action must be taken. In the absence of corrective action within a specified time, the City may move to abate or correct the problem at the owner's expense, or pursue other such remedies authorized under the laws of the State of Idaho, and this Code up to and including removal from the National Flood Insurance Program pursuant to section 1316 of the National Flood Insurance Act. In instances where such violation poses an imminent threat to public health, safety, and welfare, the City may take immediate action.
      C.   Appeal: Any owner who has received an order to take corrective action may appeal the order to the City Council by giving notice of appeal in writing to the Floodplain Administrator and the Clerk within ten (10) days following issuance of the final order. In the absence of an appeal, the order of the Floodplain Administrator shall be final. The local Governing Body shall hear an appeal within a reasonable time and may affirm, modify and affirm, or revoke the order.
      D.   Failure To Comply With Order: If the owner of a building or property fails to comply with an order to take corrective action within the time specified by said order, for which no appeal has been made or fails to comply with an order of the City Council following an appeal, said failure shall constitute a violation of this article, and shall be punishable as a violation of this article under subsection 12-15-05(8) of this article.
   (5)   Variance Procedures:
      A.   The City Council of the City of Caldwell, hereinafter referred to as the "Appeal Board", shall hear and decide requests for variances from the requirements of this article.
      B.   Variances may be issued for:
         1.   The repair or rehabilitation of historic structures upon the determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and that the variance is the minimum necessary to preserve the historic character and design of the structure;
         2.   Functionally dependent uses, if determined to meet the definition as stated in section 12-15-03 of this article, provided provisions of subsections (5)H2, (5)H3, and (5)H4(C) of this section, have been satisfied, and such facilities are protected by methods that minimize flood damages during the base flood and create no additional threats to public safety; or
         3.   Any other type of development, provided it meets the requirements of this section.
      C.   In passing upon variances, the Appeal Board shall consider all technical evaluations, all relevant factors, all standards specified in other sections of this article, and:
         1.   The danger that materials may be swept onto other lands to the injury of others;
         2.   The danger to life and property due to flooding or erosion damage;
         3.   The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;
         4.   The importance of the services provided by the proposed facility to the community;
         5.   The necessity to the facility of a waterfront location as defined under section 12-15-03 of this article as a functionally dependent use, where applicable;
         6.   The availability of alternative locations, not subject to flooding or erosion damage, for the proposed use;
         7.   The compatibility of the proposed use with existing and anticipated development;
         8.   The relationship of the proposed use to the comprehensive plan and floodplain management program for that area;
         9.   The safety of access to the property in times of flood for ordinary and emergency vehicles;
         10.   The expected heights, velocity, duration, rate of rise, and sediment transport of the floodwaters and the effects of wave action, if applicable, expected at the site; and
         11.   The costs of providing governmental services during and after flood conditions including maintenance and repair of public utilities and facilities such as sewer, gas, electrical and water systems, and streets and bridges.
      D.   The applicant shall include a written report addressing each of the factors in subsections (5)C1 through (5)C11 of this section with their application for a variance.
      E.   Upon consideration of the factors listed above and the purposes of this article, the Appeal Board may attach such conditions to the granting of variances as it deems necessary to further the purposes and objectives of this article.
      F.   Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation (BFE) and the elevation to which the structure is to be built and that such construction below the BFE increases risks to life and property, and that the issuance of a variance to construct a structure below the BFE will result in increased premium rates for flood insurance up to twenty- five dollars ($25.00) per one hundred dollars ($100.00) of insurance coverage. Such notification shall be maintained with a record of all variance actions, including justification for their issuance.
      G.   The Floodplain Administrator shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency and the State of Idaho upon request.
      H.   Conditions for variances:
         1.   Variances shall not be issued when the variance will make the structure in violation of other Federal, State, or local laws, regulations, or ordinances.
         2.   Variances shall not be issued within any designated floodway if the variance would result in any increase in flood levels during the base flood discharge.
         3.   Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
         4.   Variances shall only be issued upon:
            (A)   A showing of good and sufficient cause;
            (B)   A determination that failure to grant the variance would result in exceptional hardship; and
            (C)   A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, or extraordinary public expense, create nuisance, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
      I.   A variance may be issued for solid waste disposal facilities or sites, hazardous waste management facilities, salvage yards, and chemical storage facilities that are located in special flood hazard areas provided that all of the following conditions are met.
         1.   The use serves a critical need in the community.
         2.   No feasible location exists for the use outside the special flood hazard area.
         3.   The lowest floor of any structure is elevated or floodproofed to at least the flood protection elevation.
         4.   The use complies with all other applicable Federal, State and local laws.
      J.   The City of Caldwell will notify the State NFIP Coordinator of the Idaho Department of Water Resources of applications for a variance at least thirty (30) calendar days prior to granting the variance.
      K.   Any person aggrieved by the decision of the Appeal Board may appeal such decision to the court, as provided in Idaho Code 67-6535. (Ord. 3207, 3-4-2019)
12-15-09: PROVISIONS FOR FLOOD HAZARD REDUCTION:
   (1)   General Standards: In all special flood hazard areas the following provisions are required:
      A.   All new construction, substantial improvements, and development shall be designed (or modified) and adequately anchored to prevent flotation, collapse, and lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy.
      B.   All new construction, substantial improvements, and development shall be constructed with materials and utility equipment resistant to flood damage in accordance with the Technical Bulletin 2, Flood Damage-Resistant Materials Requirements, and available from the Federal Emergency Management Agency and applicable Idaho Building Codes.
      C.   All new construction, substantial improvements, and development shall be constructed by methods and practices that minimize flood damages.
      D.   All new and replacement electrical, heating, ventilation, plumbing, air conditioning equipment, and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding to the flood protection elevation. These include, but are not limited to, HVAC equipment, water softener units, bath/kitchen fixtures, ductwork, electric/gas meter panels/boxes, utility/cable boxes, hot water heaters, and electric outlets/switches.
      E.   All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system.
      F.   All new and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharges from the systems into floodwaters.
      G.   On-site waste disposal systems shall be located and constructed to avoid impairment to them or contamination from them during flooding.
      H.   A fully enclosed area, of new construction and substantially improved structures, which is below the lowest floor used solely for parking, access, and storage shall:
         1.   Be constructed entirely of flood resistant materials at least to the flood protection elevation; and
         2.   Include, in Zones A, AE, AH, AO, and A1-30, flood openings to automatically equalize hydrostatic flood forces on walls by allowing for the entry and exit of floodwaters. To meet this requirement, the openings must either be certified by a professional engineer or architect or meet or exceed the following minimum design criteria:
            (A)   A minimum of two (2) flood openings on different sides of each enclosed area subject to flooding;
            (B)   The total net area of all flood openings must be at least one square inch for each square foot of enclosed area subject to flooding;
            (C)   If a building has more than one enclosed area, each enclosed area must have flood openings to allow floodwaters to automatically enter and exit;
            (D)   The bottom of all required flood openings shall be no higher than one foot (1') above the interior or exterior adjacent grade;
            (E)   Flood openings may be equipped with screens, louvers, or other coverings or devices, provided they permit the automatic flow of floodwaters in both directions; and
            (F)   Enclosures made of flexible skirting are not considered enclosures for regulatory purposes, and, therefore, do not require flood openings. Masonry or flood resistant wood underpinning, regardless of structural status, is considered an enclosure and requires flood openings as outlined above.
      I.   Nothing in this article shall prevent the repair, reconstruction, or replacement of a building or structure existing on the effective date of this article and located totally or partially within the floodway, or stream setback, provided there is no additional encroachment below the flood protection elevation in the floodway, or stream setback, and provided that such repair, reconstruction, or replacement meets all of the other requirements of this article.
      J.   New solid waste disposal facilities and sites, hazardous waste management facilities, salvage yards, and chemical storage facilities shall not be permitted, except by variance as specified in subsection 12-15-07(5)I of this article. A structure or tank for chemical or fuel storage incidental to an allowed use or to the operation of a water treatment plant or wastewater treatment facility may be located in a special flood hazard area only if the structure or tank is either elevated or floodproofed to at least the flood protection elevation and certified in accordance with the provisions of subsection 12-15-07(3)C of this article.
      K.   All subdivision proposals and other development proposals shall be consistent with the need to minimize flood damage and determined to be reasonably safe from flooding.
      L.   All subdivision proposals and other development proposals shall have public utilities and facilities such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage.
      M.   All subdivision proposals and other development proposals shall have adequate drainage provided to reduce exposure to flood hazards.
      N.   All subdivision proposals and other development proposals shall have received all necessary permits from those governmental agencies for which approval is required by Federal or State law, including section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 USC 1334.
      O.   All subdivision proposals and other development proposals greater than fifty (50) lots or five (5) acres, whichever is the lesser, shall include within such proposals base flood elevation data.
      P.   When a structure is partially located in a special flood hazard area, the entire structure shall meet the requirements for new construction and substantial improvements.
      Q.   When a structure is located in multiple flood hazard zones or in a flood hazard risk zone with multiple base flood elevations, the provisions for the more restrictive flood hazard risk zone and the highest base flood elevation (BFE) shall apply.
   (2)   Specific Standards: In all special flood hazard areas where base flood elevation (BFE) data has been provided, as set forth in subsection 12-15-05(2) of this article or subsection (4) of this section, the following provisions, in addition to the provisions of subsection (1) of this section, are required:
      A.   Residential Construction: New construction, substantial improvements, and development of any residential structure (including manufactured homes) shall have the lowest floor, including basement, elevated no lower than the flood protection elevation, as defined in section 12-15-03 of this article.
      B.   Non-Residential Construction: New construction, substantial improvements, and development of any commercial, industrial, or other non-residential structure shall have the lowest floor, including basement, elevated no lower than the flood protection elevation, as defined in section 12-15-03 of this article. Structures located in Zones A, AE, AH, AO, and A1-30 may be floodproofed to the flood protection elevation in lieu of elevation provided that all areas of the structure, together with attendant utility and sanitary facilities, below the flood protection elevation are watertight with walls substantially impermeable to the passage of water, using structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. For AH and AO Zones, the floodproofing elevation shall be in accordance with subsection (6)B of this section. A registered professional engineer or architect shall certify that the floodproofing standards of this subsection are satisfied. Such certification shall be provided to the Floodplain Administrator as set forth in subsection 12-15-07(3)C of this article.
      C.   Manufactured Homes:
         1.   New and replacement manufactured homes shall be elevated so that the lowest floor of the manufactured home is no lower than the flood protection elevation, as defined in section 12-15-03 of this article.
         2.   Manufactured homes shall be securely anchored to an adequately anchored foundation to resist flotation, collapse, and lateral movement, either by certified engineered foundation system, or in accordance with the most current edition of the Idaho Division of Building Safety's "Idaho Manufactured Home Installation Standard" in accordance with Idaho Code section 44-2201(2). Additionally, when the elevation would be met by an elevation of the chassis thirty- six inches (36") or less above the grade at the site, the chassis shall be supported by reinforced piers or engineered foundation. When the elevation of the chassis is above thirty- six inches (36") in height, an engineering certification is required.
         3.   All enclosures or skirting below the lowest floor shall meet the requirements of subsections (1)H1 through (1)H2 of this section.
         4.   An evacuation plan is strongly encouraged to be developed for evacuation of all residents of all new, substantially improved, or substantially damaged manufactured home parks or subdivisions located within flood prone areas.
      D.   Additions/Improvements:
         1.   Additions and/or improvements to pre-FIRM structures: When the addition and/or improvements in combination with any interior modifications to the existing structure are:
            (A)   Not a "substantial improvement", the addition and/or improvements must be designed to minimize flood damages and must not be any more non-conforming than the existing structure; or
            (B)   A "substantial improvement", both the existing structure and the addition and/or improvements must comply with the standards for new construction.
         2.   Additions to non-compliant post-FIRM structures that are a substantial improvement with no modifications to the existing structure other than a standard door in the common wall shall require only the addition to comply with the standards for new construction.
         3.   Additions and/or improvements to non-compliant post-FIRM structures when the addition and/or improvements in combination with any interior modifications to the existing structure are:
            (A)   Not a substantial improvement, the addition and/or improvements only must comply with the standards for new construction; or
            (B)   A substantial improvement, both the existing structure and the addition and/or improvements must comply with the standards for new construction.
      E.   Recreational Vehicles: Recreational vehicles shall be either:
         1.   Temporary Placement:
            (A)   Be on site for fewer than one hundred eighty (180) consecutive days and be fully licensed and ready for highway use (a recreational vehicle is ready for highway use if it is on its wheels or jacking system, is attached to the site only by quick disconnect type utilities, and has no permanently attached additions); or
         2.   Permanent Placement:
            (A)   Recreational vehicles that do not meet the limitations of temporary placement shall meet all the requirements for new construction, as set forth in subsection (1) of this section.
      F.   Temporary Non-Residential Structures: Prior to the issuance of a floodplain development permit for a temporary structure, the applicant must submit to the Floodplain Administrator a plan for the removal of such structure(s) in the event of a flash flood or other type of flood warning notification. The following information shall be submitted in writing to the Floodplain Administrator for review and written approval:
         1.   A specified time period for which the temporary use will be permitted. Time specified may not exceed six (6) months, renewable up to one year;
         2.   The name, address, and phone number of the individual responsible for the removal of the temporary structure;
         3.   The time frame prior to the event at which a structure will be removed (i.e., immediately upon flood warning notification);
         4.   A copy of the contract or other suitable instrument with the entity responsible for physical removal of the structure; and
         5.   Designation, accompanied by documentation, of a location outside the special flood hazard area, to which the temporary structure will be moved.
         6.   Temporary structures in the floodway must provide a hydraulic and hydrology analysis along with a No-Rise Certification.
      G.   Accessory Structures (Appurtenant Structures): When accessory structures (sheds, detached garages, etc.) used solely for parking, and storage are to be placed within a special flood hazard area, elevation certificate or floodproofing certificate is required in accordance with subsection 12-15-07(3)C of this article, and the following criteria shall be met:
         1.   Accessory structures shall not be used for human habitation (including working, sleeping, living, cooking, or restroom areas);
         2.   Accessory structures shall not be temperature-controlled;
         3.   Accessory structures shall be designed to have low flood damage potential;
         4.   Accessory structures shall be constructed and placed on the building site so as to offer the minimum resistance to the flow of floodwaters;
         5.   Accessory structures shall be firmly anchored in accordance with the provisions of subsection (1)A of this section;
         6.   All utility equipment and machinery, such as electrical, shall be installed in accordance with the provisions of subsection (1)D of this section; and
         7.   Flood openings to facilitate automatic equalization of hydrostatic flood forces shall be provided below flood protection elevation in conformance with the provisions of subsection (1)H of this section.
         8.   Accessory structures not used solely for parking, access, and storage must be elevated per subsections (2)A through (2)B of this section.
An accessory structure with a footprint less than two hundred (200) square feet and is a minimal investment of seven thousand five hundred dollars ($7,500.00) or less and satisfies the criteria outlined in subsections (2)G1 through (2)G7 of this section is not required to provide the elevation certificate per subsection (2)B of this section.
      H.   Tanks: When gas and liquid storage tanks are to be placed within a special flood hazard area, the following criteria shall be met:
         1.   Underground tanks in flood hazard areas shall be anchored to prevent flotation, collapse, or lateral movement resulting from hydrodynamic and hydrostatic loads during conditions of the base flood, including the effects of buoyancy (assuming the tank is empty);
         2.   Elevated above-ground tanks, in flood hazard areas shall be attached to and elevated to or above the design flood elevation on a supporting structure that is designed to prevent flotation, collapse, or lateral movement during conditions of the base flood. Tank-supporting structures shall meet the foundation requirements of the applicable flood hazard area;
         3.   Not elevated above-ground tanks may be permitted in flood hazard areas provided the tanks are anchored or otherwise designed and constructed to prevent flotation, collapse or lateral movement resulting from hydrodynamic and hydrostatic loads during conditions of the design flood, including the effects of buoyancy assuming the tank is empty and the effects of flood-borne debris;
         4.   Tank inlets, fill openings, outlets and vents shall be:
            (A)   At or above the flood protection elevation or fitted with covers designed to prevent the inflow of floodwater or outflow of the contents of the tanks during conditions of the base flood; and
            (B)   Anchored to prevent lateral movement resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy, during conditions of the base flood.
      I.   Construction Of Below-Grade Crawlspace:
         1.   The interior grade of a below-grade crawlspace must not be more than two feet (2') below the exterior lowest adjacent grade (LAG).
         2.   The height of the below-grade crawlspace, measured from the interior grade of the crawlspace to the top of the crawlspace foundation wall, must not exceed four feet (4') at any point.
         3.   There must be an adequate drainage system that removes floodwaters from the interior area of the crawlspace. The enclosed area should be drained within a reasonable time after a flood event.
         4.   The velocity of floodwaters at the site should not exceed five feet (5') per second for any crawlspace.
         5.   See FEMA Technical Bulletin 11 for further information. Buildings that have below-grade crawlspaces will have higher flood insurance premiums than buildings that have the preferred crawlspace construction, with the interior elevation of the crawlspace soil at or above the base flood elevation (BFE).
      J.   Other Development In Regulated Floodways:
         1.   Fences that have the potential to block the passage of floodwaters in regulated floodways shall meet the limitations of subsection (5) of this section.
         2.   Retaining walls, solid walls, sidewalks, and driveways that involve the placement of fill in regulated floodways shall meet the limitations of subsection (5) of this section.
         3.   Roads and watercourse crossings, including roads, bridges, culverts, low-water crossings, and similar means for vehicles or pedestrians to travel from one side of a watercourse to the other side, which propose the addition of fill which may encroach into regulated floodways, shall meet the limitations of subsection (5) of this section.
         4.   Permanently installed infrastructure utilized for drilling water, oil, and/or gas wells including fuel storage tanks, and any appurtenant equipment at the site that encroach into regulated floodways shall meet the limitations of subsection (5) of this section.
         5.   Docks, piers, boat ramps, marinas, moorings, decks, docking facilities, port facilities, shipbuilding, and ship repair facilities with potential to obstruct flow and encroach into regulated floodways shall meet the limitations of subsection (5) of this section.
   (3)   Standards For Floodplains Without Established Base Flood Elevations: Within the special flood hazard areas designated as Zone A (also known as Unnumbered A Zones) and established in subsection 12-15-05(2) of this article, where no base flood elevation (BFE) data has been provided by FEMA, the following provisions, in addition to the provisions of subsection (1) of this section, shall apply:
The BFE used in determining the flood protection elevation (FPE) shall be determined based on the following criteria:
      A.   When base flood elevation (BFE) data is available from other sources, all new construction and substantial improvements within such areas shall also comply with all applicable provisions of this article and shall be elevated or floodproofed in accordance with standards in subsections (1) through (2) of this section.
      B.   When floodway data is available from a Federal, State, or other source, all new construction and substantial improvements within floodway areas shall also comply with the requirements of subsections (2) and (5) of this section.
      C.   Require that all new subdivision proposals and other proposed developments (including proposals for manufactured home parks and subdivisions) greater than fifty (50) lots or five (5) acres, whichever is the lesser, include within such proposals base flood elevation data. Such base flood elevation (BFE) data shall be adopted by reference in accordance with subsection 12-15-05(2) of this article and utilized in implementing this article. See FEMA 480 and/or FEMA 265 for further information.
      D.   When base flood elevation (BFE) data is not available from a Federal, State, or other source as outlined above, the lowest floor shall be elevated or floodproofed (non- residential) to two feet (2.0') above the highest adjacent grade (HAG) at the building site or to the flood protection elevation (FPE) whichever is higher, as defined in section 12-15-03 of this article. All other applicable provisions of subsection (2) of this section shall also apply.
   (4)   Standards For Riverine Floodplains With Base Flood Elevations But Without Established Floodways: Along rivers and streams where base flood elevation (BFE) data is provided by FEMA or is available from another source but floodways are not identified for a special flood hazard area on the FIRM or in the FIS report, the following requirements shall apply to all development within such areas:
      A.   Standards of subsections (1) and (2) of this section; and
      B.   Until a regulatory floodway is designated, no encroachments, including fill, new construction, substantial improvements, or other development shall be permitted unless certification with supporting technical data by a registered professional engineer is provided demonstrating that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood at any point within the community.
   (5)   Standards For Floodways: Areas designated as floodways located within the special flood hazard areas established in subsection 12-15-05(2) of this article. The following provisions, in addition to standards outlined in subsections (1) and (2) of this section, shall apply to all development within such areas:
      A.   No encroachments, including fill, new construction, substantial improvements, and other developments shall be permitted unless:
         1.   It is demonstrated that the proposed encroachment would not result in any increase in the flood levels during the occurrence of the base flood, based on hydrologic and hydraulic analyses performed in accordance with standard engineering practice and presented to the Floodplain Administrator prior to issuance of floodplain development permit (This is a No-Rise Analysis and Certification.); or
         2.   A Conditional Letter of Map Revision (CLOMR) has been approved by FEMA. A Letter of Map Revision (LOMR) must also be obtained within six (6) months of completion of the proposed encroachment.
      B.   If subsection (5)A of this section is satisfied, all development shall comply with all applicable flood hazard reduction provisions of this article.
      C.   Manufactured homes may be permitted provided the following provisions are met:
         1.   The anchoring and the elevation standards of subsection (2)C of this section; and
         2.   The encroachment standards of subsection (5)A of this section.
   (6)   Standards For Areas Of Shallow Flooding (Zone AO, AH, AR/AO, Or AR/AH): Areas designated as shallow flooding areas have special flood hazards associated with base flood depths of one foot (1') to three feet (3') where a clearly defined channel does not exist and where the path of flooding is unpredictable and indeterminate. In addition to subsections (1) and (2) of this section, all new construction and substantial improvements shall meet the following requirements:
      A.   The lowest floor shall be elevated at least as high as the depth number specified on the Flood Insurance Rate Map (FIRM), in feet, plus a freeboard of one foot (1'), above the highest adjacent grade; or at least two feet (2') above the highest adjacent grade if no depth number is specified.
      B.   Non-residential structures may, in lieu of elevation, be floodproofed to the same level as required in subsection (6)A of this section so that the structure, together with attendant utility and sanitary facilities, below that level shall be watertight with walls substantially impermeable to the passage of water and with structural components having the capability of resisting hydrostatic and hydrodynamic loads and effects of buoyancy. Certification is required in accordance with subsections 12-15-07(3)C and (2)B of this article.
      C.   Accessory structure (appurtenant structure) (sheds, detached garages, etc.):
         1.   Used solely for parking, access, and storage:
            (A)   Shall have the lowest floor elevated at least as high as the depth number specified on the Flood Insurance Rate Map (FIRM); or at least two feet (2') above the highest adjacent grade if no depth number is specified; or
            (B)   Shall have flood openings to facilitate automatic equalization of hydrostatic flood forces shall be provided below flood protection elevation in conformance with the provisions of subsection (1)H of this section.
         2.   Not used solely for parking, access, and storage:
            (A)   Shall be elevated per subsections (2)A through (2)B of this section.
      D.   Adequate drainage paths shall be provided around structures on slopes to guide floodwaters around and away from proposed structures. (Ord. 3207, 3-4-2019)
12-15-11: LEGAL STATUS PROVISIONS:
   (1)   Effect On Rights And Liabilities Under The Existing Flood Damage Prevention Ordinance: This article, in part, comes forward by re-enactment of some of the provisions of the Flood Damage Prevention Ordinance enacted May 2, 1975 as amended, and it is not the intention to repeal but rather to re-enact and continue to enforce without interruption of such existing provisions, so that all rights and liabilities that have accrued thereunder are reserved and may be enforced. The enactment of this article shall not affect any action, suit, or proceeding instituted or pending. All provisions of the Flood Damage Prevention Ordinance of the City of Caldwell enacted on May 2, 1975, as amended, which are not reenacted herein are repealed.
   (2)   Effect Upon Outstanding Floodplain Development Permits: Nothing herein contained shall require any change in the plans, construction, size, or designated use of any development or any part thereof for which a floodplain development permit has been granted by the Floodplain Administrator or his or her authorized agents before the time of passage of this article. Provided, however, that when construction is not begun under such outstanding permit within a period of one hundred eighty (180) days subsequent to the date of issuance of the outstanding permit, construction or use shall be in conformity with the provisions of this article. (Ord. 3207, 3-4-2019)
ARTICLE 17
PUBLIC RIGHTS OF WAY IMPROVEMENTS
SECTION:
12-17-01: Legislative Purpose
12-17-02: Minimum Improvements Required
12-17-03: Rules And Regulations
12-17-04: Deferral Standards
12-17-05: Right Of Way Permits
12-17-06: Financial Guarantee Requirements
12-17-07: Nuisance
12-17-01: LEGISLATIVE PURPOSE:
The city council finds that the improvement of previously unimproved real properties increases pedestrian and vehicular traffic to and from said properties, necessitates a provision for the delivery of water and disposal of sanitary sewage, necessitates the provision for the control of stormwater, surface water and other drainage to ensure the orderly flow of surface waters for the protection of adjoining properties and the protection of roads and streets servicing said property; and therefore it is hereby found to be in the best interest of the health, safety and welfare of the citizens of Caldwell to require certain minimum road improvements and right of way dedication, the installation of curbs, gutters and sidewalks, and to require a connection to the city sewer and water systems (when available) and to facilitate ready connection to city services (when not presently available) as a condition precedent to obtaining a building permit and in this regard to regulate the placement of underground utilities. (Ord. 2794, 7-20-2009)
Loading...