§ 155.015 CONSTRUCTION PERMITS IN THE FLOODWAY.
   (A)   I.C. 14-28-1-22, requires Natural Resources Commission approval of any construction in a floodway, and of any works for flood control. This includes bridges, dams, levees, dikes, floodwalls, wharves, piers, dolphins, booms, weirs, bulkheads, jetties, groins, excavations, fills or deposits of any kind, utility lines, or any other building, structure or obstruction; also, any ditch work (new construction, deepening or modification) within 1/2 mile of a public freshwater lake of 10 acres or more in area.
   (B)   The approval of the Natural Resources Commission, in writing, must be obtained before beginning construction. Applications for approval should be submitted to:
Department of Natural Resources
Division of Water
Indianapolis, Indiana
   (C)   All applications should be made on the standard application form provided by the Commission and should be accompanied by plans, profiles, specifications and other data necessary for the Commission to determine the effect of the proposed construction upon the floodway and on flood control in the state.
   (D)   Application made to and approval granted by the Natural Resources Commission does not in any way relieve the owner of the necessity of securing easements or other property rights, and permits and/or approvals from affected property owners and local, state and federal agencies.
   (E)   The engineering staff of the Division of Water is available to discuss and offer suggestions regarding requirements in the design of structures in floodways. High water marks have been set on many of the streams in the state, and information is available from the Division of Water on actual and/or potential flooding. Information regarding benchmarks set to Mean Sea Level Datum, General Adjustment of 1929, is available from the Division of Water, Surveying and Mapping Section.
   (F)   Applications are considered by the Commission at regular meetings usually held each month. After the application and plans have been approved by the Commission, a certificate of approval is forwarded to the applicant.
   (G)   A fee is charged by the Commission for approvals under I.C. 14-28-1-22. Unless stated otherwise in the approval, construction is considered to be a permanent development, and no renewals of the approval are necessary, except in the cases where temporary approvals are granted for temporary construction. The right is reserved to require additional data where necessary.
(Ord. 1995-10 § VI, passed 10-13-1995)