(a) Pre-Application Meeting. The owner is encouraged to schedule a meeting with the Village Engineer or his or her designated representative to:
(1) Discuss the proposed project;
(2) Review the requirements of this chapter;
(3) Identify unique aspects of the project that must be addressed during the review process;
(4) Establish a preliminary review and approval schedule.
(b) Preliminary Comprehensive Stormwater Management Plan. The applicant shall submit two sets of a preliminary comprehensive stormwater management plan (preliminary plan) and the applicable fees to the Village Engineer. The preliminary plan shall show the proposed property boundaries, setbacks, dedicated open space, public roads, water resources, stormwater control facilities, and easements in sufficient detail and engineering analysis to allow the Village Engineer to determine if the site is laid out in a manner that meets the intent of this regulation and if the proposed stormwater management practices are capable of controlling runoff from the site in compliance with this regulation. The applicant shall submit two sets of the preliminary plan and applicable fees as follows:
(1) Subdivisions. In conjunction with the submission of the preliminary subdivision plan.
(2) Other construction projects. In conjunction with the application for a building permit.
(3) All stormwater management plans that are part of proposed development sites subject to this regulation, and which meet the following criteria, must also submit all written documents, calculations and engineering drawings that establish the stormwater management for the site to the Northeast Ohio Regional Sewer District (NEORSD) within seven business days of submittal to the Village Engineer.
A. The site must be located within NEORSD's Stormwater Service Area.
B. The site is located outside NEORSD's combined sewer system.
(c) Final Comprehensive Stormwater Management Plan. The applicant shall submit two sets of a final comprehensive stormwater management plan (final plan) and the applicable fees to the Village Engineer in conjunction with the submittal of the final plat, improvement plans, or application for a building or building permit for the site. The final plan shall meet the requirements of Section 1050.13
and shall be approved by the Village Engineer prior to approval of the final plat and/or before issuance of a building permit by the Building Inspector.
(d) Review and Comment. The Village Engineer shall review the preliminary and final plans submitted, and shall approve or return for revisions with comments and recommendations for revisions. A preliminary or final plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised preliminary or final plan.
(f) Sub-lots Will Not Proceed. Comprehensive stormwater management plans for individual sub-lots in a subdivision will not be approved and building permits will not be issued unless the larger common plan of development or sale containing the sub-lot is in compliance with this regulation.
(g) Valid for Two Years. Approvals issued in accordance with this regulation shall remain valid for two years from the date of approval.
(Ord. 63-2017. Passed 12-5-17.)