1321.07 PROCEDURES TO CREATE PLANNED UNIT DEVELOPMENT.
   (a)   A planned unit development plan, including a site map shown to scale with all supporting text shall be submitted to the Zoning Code Official.
   (b)   The City shall then schedule a meeting with the applicant, City Engineer and Zoning Code Official to discuss and review the planned unit development request.
   (c)   The project shall be presented to the Planning Commission for review and discussion at its next regular scheduled meeting.
   (d)   The Planning Commission shall then set a public hearing in accordance with Section 1309.01(c).
   (e)   After said public hearing, the Commission shall submit a report and recommendation on the project to Council for formal action.
   (f)   Council shall take final action. If approval is granted, Council shall have two readings of an ordinance creating the planned unit development as an amendment to the official Zoning Map of the City. If Council denies the project, it shall submit reasons in writing stating why and offering potential modifications. The applicant may then take the project back to the Planning Commission with the modifications and start the process again.
   (g)   With Council approval, the project moves to the construction phase. All infrastructure shall have construction drawings submitted to the City Engineer for review in conformance with Section 1341.02. All infrastructure shall be inspected and approved by the City Engineer or his duly authorized agent in accordance with Section 1341.02. Once infrastructure is complete and approved, or bonded and approved by the City Engineer, the Code Official shall be notified in writing that compliance has been achieved.
   (h)   The Code Official shall then have the planned unit development duly recorded by the county jurisdiction.
   (i)   Once all applicable plats are recorded, requests for building permits can be made in accordance with the State Building Code.
(Ord. 6-00. Passed 8-14-00.)