Section 104.4.4 of the "Idaho State Plumbing Code" is hereby repealed and replaced to read as follows:
104.4.4 Extensions. Any holder of an unexpired permit may apply for an extension of time within which work may commence under that permit, when the permittee is unable to commence work within the time required by this Chapter. The code official may extend the time to request an extension for a period not exceeding 180 calendar days on written request by the permittee demonstrating a good faith effort to complete the project has been made and that reasons beyond the control of the permittee have resulted in delay. Under no condition shall a permit be extended more than three times, for a total maximum of three 180 day extensions. Each 180-day extension must be approved individually by the code official.
(Ord. 20-19, 6-11-2019)