1256.11 EXPIRATION OF AUTHORIZATION.
   (a)    If no construction has begun within one year of final approval of the PUD Final Development Plan, the approval shall expire. The Board of Zoning and Planning may extend approval for an additional one-year period if an application for extension is received before the authorization expires. If no construction has begun at the end of this extension, the Final Development Plan shall become null and void, and a new one shall be required for any development on subject property.
   (b)    Upon the abandonment of a particular project authorized under this chapter or upon the expiration of two years from the final approval of a PUD which has not by then been completed or commenced with an extension of time for completion granted, the authorization shall expire and revert back to the previous zoning, thus the land and the structures thereon may be used only for a lawful purpose permissible within that previous zoning category.
(Ord. 29-16. Passed 11-15-16; Ord. 08-20. Passed 7-14-20.)