1312.09 CHANGE IN RESIDENTIAL PLANS, WORK STARTED WITHOUT PERMITS, AND RE-INSPECTION FEE.
 
A
CHANGE IN PLANS:
50% OF ORIGINAL FEE
WHEN MAJOR REVISIONS ARE DECIDED ON AFTER THE ORIGINAL CONSTRUCTION PERMIT(S) HAVE BEEN ISSUED FOR PERMITS ISSUED UNDER SECTION 1311.01 THRU 1311.08, AN ADDITIONAL FEE OF THE ORIGINAL CONSTRUCTION PERMIT FEE(S) SHALL BE COLLECTED FOR CONSIDERATION OF SUCH REVISIONS
B
WORK STARTED WITHOUT PERMITS:
Double Fee
WHEN WORK HAS STARTED PRIOR TO OBTAINING THE NECESSARY PERMITS REQUIRED UNDER SECTION 1311.01 THRU 1311.08, THE PERMIT FEE(S) SHALL BE DOUBLED THE COST FOR ALL PERMITS REQUIRED
C
RE-INSPECTION:
$25.00 PER INSPECTION
WHEN AN INSPECTION IS REQUESTED AND IS MADE AND THE WORK IS FOUND TO BE EITHER INCOMPLETE OR NOT IN CONFORMITY WITH THE APPLICABLE CODE(S) OR WITH ANY APPROVED SPECIFICATIONS OR PLANS, A CHARGE SHALL BE MADE FOR REINSPECTION FOUND NECESSARY BY THE BUILDING INSPECTOR
(Ord. 2018-17. Passed 4-2-18.)