BASE FEE | SQUARE FOOTAGE FEE | 1% BBS FEE | ||
A | ONE, TWO AND THREE BASE TOPO REVIEW FEE/LOT | $300.00 | N | |
B | ENGINEERING DEPARTMENT SUBDIVISION REVIEW FEES: | |||
1 | PER LOT UP TO FIRST 100 LOTS | $500.00 | N | |
2 | LOT FOR EACH THEREAFTER | $200.00 | N | |
C | DETAILED INSPECTION REPORT | $100.00 | N | |
D | SUBSOIL DRAINAGE POINT OF DISCHARGE | $30.00 | N | |
E | FINAL GRADING BOND | $1,000.00 | N | |
RESIDENTIAL: A $1000 CASH GRADING BOND SHALL BE SUBMITTED FOR EACH DWELLING UNIT BY THE BUILDER | ||||
F | ENGINEERING INSPECTION | $45.00 PER HOUR ENGINEERING DEPARTMENT INSPECTION FOR ALL UTILITY AND SUBDIVISION CONSTRUCTION | ||
(Ord. 2018-17. Passed 4-2-18.)