§ 155.445 EXPIRATION OF A PERMIT.
   (A)   Whenever a zoning permit or conditional zoning permit is issued, the construction under such permit shall begin within six months after issuance and shall be completed within 18 months after issuance.
   (B)   Upon written application and upon the showing of good cause to the Planning Commission, an additional period of time to begin or complete construction may be granted. Whenever construction is not begun or completed within the time specified in this section including any extension granted by the Planning Commission, the zoning permit or conditional zoning permit shall expire and no further use of the land for which such a permit is required shall be allowed until another permit is issued.
(Ord. 87-27, § 806, passed 7-7-1987)