§ 153.008 PLAN REVIEW.
   (A)   The VA shall review the stormwater management plan or drainage plan within 30 days of receipt and indicate his or her approval or disapproval to the person who filed the plan. Indication of disapproval shall include the plan deficiencies and the procedure for filing a revised plan. Pending preparation and approval of a revised plan, earth-disturbing activities shall not be allowed until the deficiencies have been properly addressed.
   (B)   During the plan review, the VA may request recommendations pertaining to the proposed plan from the Village Engineer and the County Regional Planning Commission. The Village Engineer shall be responsible for review and approval of all hydrological and runoff calculations as well as design and construction inspection for all stormwater management facilities.
(Ord. 16-96, passed 4-15-1996)