§ 51.048 INSPECTION OF WORK; REPORT OF WORK DONE.
   (A)   The Sewer Superintendent shall be given notice when any work is ready for inspection, and all work must be left uncovered and convenient for examination until inspected and approved. The inspection shall be made within 24 hours after the notification. The Sewer Superintendent shall apply the ether, peppermint, water, or smoke test, and the plumber shall furnish all necessary tools, labor, and assistants for these tests. The plumber shall remove or repair any defective material or labor when so ordered by the Sewer Superintendent.
('67 Code, § 51.14)
   (B)   The plumber shall, on completion of the work, file in the office of the Sewer Superintendent on blanks furnished for the purpose, a correct statement of the work done under the permit.
('67 Code, § 51.15) (Ord. 28-1931, passed 7-21-03) Penalty, see § 51.999