(A) Plans and application requirements. Application for a floodplain development permit shall be made to the Floodplain Administrator on forms furnished by him or her prior to any development activities proposed to be located within flood-prone areas. The following items/information may be required by the Floodplain Administrator to apply for a floodplain development permit:
(1) A plot plan drawn to scale which shall include, but shall not be limited to, the following specific details of the proposed floodplain development:
(a) The nature, location, dimensions, and elevations of the area of development/disturbance; existing and proposed structures, the location of utility systems, proposed grading/pavement areas, fill materials, storage areas, drainage facilities, and other proposed development;
(b) The boundary of the special flood hazard area as delineated on the FIRM or other flood map as determined in § 152.07 or a statement that the entire lot is within the special flood hazard area;
(c) Flood zone(s) designation of the proposed development area as determined on the FIRM or other flood map as determined in § 152.07;
(d) The boundary of the floodway(s) or non-encroachment area(s) as determined in § 152.07;
(f) The old and new location of any watercourse that will be altered or relocated as a result of proposed development; and
(g) Preparation of the plot plan by or under the direct supervision of a registered land surveyor or professional engineer and certified by the same.
(2) Proposed elevation, and method thereof, of all development within a special flood hazard area including but not limited to:
(a) Elevation in relation to mean sea level of the proposed reference level (including basement) of all structures;
(b) Elevation in relation to mean sea level to which any non-residential structure will be flood-proofed; and/or
(c) Elevation in relation to mean sea level to which any proposed utility systems will be elevated or flood-proofed.
(4) A foundation plan drawn to scale which shall include details of the proposed foundation system to ensure all provisions of this chapter are met. These details include but are not limited to:
(a) Proposed method of elevation, if applicable (i.e., fill, solid foundation perimeter wall, solid backfilled foundation, open foundation on columns/piers); and/or
(b) Should solid foundation perimeter walls be used in floodplains, details of sufficient openings to facilitate the unimpeded movements of floodwaters in accordance with § 152.46(D).
(5) Usage details of any enclosed space below the regulatory flood protection elevation;
(6) Copy of all other local, state, and federal permits required prior to floodplain development permit issuance (i.e., wetlands, erosion and sedimentation control, riparian buffers, mining, and the like);
(7) If a floodplain development permit is issued for placement of recreational vehicles and/or temporary structures, documentation to ensure § 152.46(F) and (G) are met; and
(8) If a watercourse is proposed to be altered and/or relocated, a description of the extent of watercourse alteration or relocation, an engineering report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream, and a map (if not shown on plot plan) showing the location of the proposed watercourse alteration or relocation.
(B) Floodplain development permit data requirements. The following information shall be provided at a minimum on the floodplain development permit to ensure compliance with this chapter:
(1) A description of the development to be permitted under the floodplain development permit issuance;
(2) The special flood hazard area determination for the proposed development per available data specified in § 152.07;
(3) The regulatory flood protection elevation required for the reference level and all attendant utilities;
(4) The regulatory flood protection elevation required for the protection of all public utilities;
(5) All certification submittal requirements with timelines;
(6) State that no fill material shall encroach into the floodway or non-encroachment area of any watercourse, if applicable;
(7) State limitations of below BFE enclosure uses (if applicable), (i.e., parking, building access, and limited storage only);
(8) If in an A, AO, AE, or A1-30 Zone, specify the minimum foundation opening requirements; and
(9) State limitations of below BFE enclosure uses (if applicable), (i.e., parking, building access, and limited storage only).
(C) Certification requirements.
(1) A benchmark must be established on the project site locating the regulatory flood protection elevation. A certified letter outlining the elevation details in relation to mean sea level of this benchmark must be submitted to the Floodplain Administrator prior to permit issuance. Said certification shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same.
(2) A final as-built elevation certificate (FEMA Form 81-31) or flood-proofing certificate (FEMA Form 81-65) is required after construction is completed and prior to certificate of compliance/occupancy issuance. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of final as-built construction of the elevation or flood-proofed elevation of the reference level and all attendant utilities. Said certification shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by the same. When flood- proofing is utilized, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to certificate of compliance/occupancy issuance. In some instances, another certification may be required to certify corrected as-built construction. Failure to submit the certification or failure to make said corrections required shall be cause to withhold the issuance of a certificate of compliance/occupancy.
(3) If a manufactured home is placed within an A, AO, AE, or A1-30 Zone and the elevation of the chassis is above 36 inches in height, an engineered foundation certification is required per § 152.46(C).
(4) If a watercourse is to be altered or relocated, a description of the extent of watercourse alteration or relocation, an engineering report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream, and a map showing the location of the proposed watercourse alteration or relocation shall all be submitted by the permit applicant prior to issuance of a floodplain development permit.
(5) The following structures, if located within A, AO, AE, or A1-30 Zones, are exempt from the elevation/flood-proofing certification requirements specified in divisions (C)(1) and (C)(2) above:
(a) Recreational vehicles meeting requirements of § 152.46(F)(1);
(b) Temporary structures meeting requirements of § 152.46(G); and
(c) Accessory structures less than 150 square feet meeting requirements of § 152.46(H).
(Ord. passed 5-5-2003)