11-7-2: AMENDMENTS:
The following sections are amendments or modifications to the Kane County stormwater management ordinance, and correspond to the numbering system within said ordinance:
Section 203(a): New sections to be added as follows:
203(a)(1) Areas within the McKee tributary sub-basin the release rate shall not exceed 0.07 CFS/acre.
203(a)(2) For areas tributary to the Batavia Highlands sewer system the release rate shall not exceed 0.08 CFS/acre.
Section 500(c): Amend to read as follows:
The following permit fee shall be paid at the time of application: one hundred dollars ($100.00) for administration of the permit. The developer (permittee) shall agree to pay all review and inspection costs prior to, during and after construction through the time of final acceptance by the city council. Payments shall be made within thirty (30) days of invoicing. Failure to pay within the time allotted shall result in the stoppage of all work on the development until such time as all payments due are current.
Section 902: Amend to read as follows:
With the filing of the application for a variance, the applicant shall pay a fee of two hundred fifty dollars ($250.00). The applicant shall agree to pay all consultant review costs throughout the variance process until completion. Payment shall be made within thirty (30) days of invoicing. Failure to pay within the time allotted shall result in the stoppage of all work on the development until such time as all payments due are current.
Section 1002: New section (p) to be added as follows:
The administrator is hereby designated to be the city engineer of the city of Batavia.
Section 1004: Amend to read as follows:
Oversight Committee. There is hereby established an oversight committee to oversee the implementation and enforcement of this ordinance within the city of Batavia, and to perform the duties assigned to the oversight committee in this ordinance. The oversight committee is hereby designated to be the public services committee of the city council of the city of Batavia. The oversight committee, when considering an appeal or request for a variance under this ordinance, may request an opinion from a qualified engineer review specialist or qualified wetland review specialist on technical issues.
Section 1005: Amend to read as follows:
Decision-Making Authority. There is hereby established a decision-making authority to perform the duties assigned to the decision-making authority in this ordinance. The decision-making authority is hereby designated to be the city council of the city of Batavia. The decision-making authority, when considering an appeal or request for a variance under this ordinance, may request an opinion from a qualified engineer review specialist or qualified wetland review specialist on technical issues.
Section 1201(c): Amend to read as follows:
The administrator may approve periodic reductions in the amount of security based upon the progress of construction. At no time, however, shall more than 75% of the security be released prior to approval of record drawings and final inspection. A minimum of 25% of the original amount of the security shall be retained for a period of one year after completion of all required storm water facilities.
Section 1300: Amend to read as follows:
Fee-in-lieu of site runoff storage
The administrator may require, or in the limited circumstances prescribed in article 2 an applicant may request approval of, the payment of a fee-in-lieu of site runoff storage to fulfill all or part of the site runoff storage requirement for a development. The fee to be paid in lieu of site runoff storage shall be the verifiable cost of otherwise providing the required storage, including the value of the land required and all construction costs. For this purpose the land required shall be valued according to the use to which it will ultimately be put if not used to provide the required storage.
   (Ord. 01-36, 6-18-2001)