9-4-2: APPLICATION SUBMITTAL PROCEDURES AND CONTENTS:
Procedures for final plat/replat approval are as follows:
   A.   No final plat shall be considered unless submitted within six (6) months of preliminary plat approval by the council. If the council placed conditions on the approval of the preliminary plat, all conditions must be met on the final plat application prior to the application being submitted to the town clerk.
   B.   Persons submitting final plat/replat applications are required to discuss their applications, upon the request of the town engineer, prior to submitting the application for review. The purpose of the meeting shall be to advise such person of the requirements and procedures for final plat or replat approval.
   C.   After the owner/staff meeting, a complete application consisting of fifteen (15) eleven inch by seventeen inch (11" x 17") copies of the final plat must be submitted to the town engineer, and the following:
      1.   The original and three (3) twenty four inch by thirty six inch (24" x 36") copies of a final plat/replat application form;
      2.   All revisions, changes, additions, and data needed to meet conditions placed on the preliminary plat by the council;
      3.   Proof of ownership of the land in question, such as a title policy, a letter from a title company certifying ownership, or an attorney's opinion;
      4.   The erosion control plan shall be prepared in accordance to DEQ standards and available to the town as requested. (Ord. 2012-04, 7-17-2012)