7-2-6: ADMINISTRATION AND ENFORCEMENT:
   A.   Administration:
      1.   This Chapter shall be administered by the Town.
      2.   The application for a solar rights permit, along with the required fee, shall be filed on forms provided by the Town.
      3.   Zoning and Planning shall approve a solar access permit for any solar collector which complies with this Chapter.
      4.   An approved solar access permit and site plan shall be filed in the Natrona County Clerk's office within three (3) working days after Zoning and Planning approves the solar rights application and site plan. A recording fee for filing the permit application and site plan, made payable to the Natrona County Clerk, shall be submitted to the Town. Zoning and Planning shall be responsible for recording the permit application and site plan. The application and site plan shall become effective after being recorded in the County Clerk's office.
      5.   One copy of the permit and site plan shall be returned to the applicant, and one copy shall remain on file in the Town.
      6.   Zoning and Planning shall also notify all surrounding property owners by letter before a solar access permit has been granted. A hearing shall be held at the request of any member of Zoning and Planning or any interested party.
   B.   Enforcement:
      1.   Once a solar collector conforming to this Chapter has been constructed and the permit approved by the Town and recorded in the County Clerk's office, then a solar property right is established.
      2.   The building inspector or other administrative official shall enforce this Chapter and bring to the attention of the Town Attorney any violations or lack of compliance. (Ord. 88-03, 6-7-1988)
      3.   Any person violating any provision of this Chapter shall be punished by a fine as provided in Section 1-4-1 of this Code. If any violation be continuing, each day's violation shall be deemed a separate offense. (Ord. 88-03, 6-7-1988; amd. 1999 Code)