§ 156.49 CERTIFICATION.
   At the completion of the improvements approved in the stormwater management plan, the applicant shall provide to the Flood Safety Officer a certification by a professional engineer that the improvements have been built in conformance with the plan. No Certificate of Occupancy will be issued or performance bond released prior to receipt of certification. A set of As-built drawings shall also be provided within 30 days of completion of the project. In instances where there are improvements that are to become part of the public infrastructure system, digital copies shall also be provided.
(Ord. 432, passed 5-16-90; Am. Ord. B2006-8, passed 5-23-06; Am. Ord. B2011-19, passed 9-27-11)