1230.09 TERMS AND DURATION OF SPECIAL USE PERMIT.
   Following Council’s approval of an application for a Special Use permit, the Zoning Enforcement Officer shall provide a copy of the signed ordinance authorizing the Special Use Permit.
   (a)   The permit/ordinance shall authorize a particular Special Use on the specific parcel for which it was approved. The permit/ordinance shall be valid only for the use and the operation of such use as specified on the permit. The breach of any condition, safeguard or requirement shall constitute a violation of this Planning and Zoning Code.
   (b)   The Special Use permit shall expire one year from the date of enactment unless the following occur:
      (1)   The final development plan is approved for uses that require a final development plan;
      (2)   Construction in the establishment of the use has begun. Construction is deemed to have begun when all necessary excavation and piers or footings of the structure included in the application have been completed; or
      (3)   As otherwise specifically approved by the Planning Commission.
   (c)   Any expansion, enlargement, or change in the operation of the Special Use that involves enlarging buildings or structures, expanding impervious surfaces, including parking areas, or changing the use shall require approval of a separate Special Use permit and revised development plan.
(Ord. 58-01. Passed 5-29-01; Ord. 76-16. Passed 7-11-16.)