108.05 UNACCEPTABLE GROUNDS.
   Grounds that will not be considered as a basis for approving a change order include, but are not limited to, the following:
   (a)   Loss of anticipated profit on part of contractor.
   (b)   Delays caused by weather.
   (c)   Delays caused by employee strikes and/or withholding of work.
   (d)   Equipment availability and/or capabilities.
   (e)   Material shortages during contract period.
   (f)   Architectural fee recovery in amounts that exceed agreed maximum cost.
   (g)   Engineering fee recovery in amounts that exceed agreed maximum cost.
   (h)   Material quantity and/or quality.
   (i)   Accepted design elements.
      (Ord. 2008-216. Passed 12-15-08.)